The sponsor asks you to skip the final round of user acceptance testing (UAT) to meet the deadline, stating that earlier tests were sufficient. What should the project manager do first?

⚠ Common exam trap

Many exam-takers assume the sponsor's authority is absolute (leading to option A) or that escalation is the immediate step (option D), but the PMP exam emphasizes that the project manager should first engage the sponsor with a reasoned analysis and collaborative solution.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Explain the risks of skipping UAT and propose alternatives, such as reducing test scope or compressing the schedule

The project manager must first address the sponsor's request by explaining the risks of skipping UAT, which validates that the system meets user requirements and functions correctly in a production-like environment. Proposing alternatives like reducing test scope or compressing the schedule demonstrates proactive risk management while keeping the project aligned with quality standards. Skipping UAT entirely could lead to undetected defects, user dissatisfaction, and costly rework post-deployment.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Direct the team to proceed without UAT because the sponsor has authority

    Why it's wrong here

    Directing the team to proceed without UAT solely because the sponsor has authority is an abdication of the Project Manager's professional responsibility. The PM is accountable for advocating for project quality, adhering to the established project management plan, and managing identified risks. Blindly following a request that compromises a critical quality gate, even from a sponsor, fails to uphold the PM's duty to protect project outcomes and stakeholder value.

  • Agree to skip UAT to accommodate the sponsor's request

    Why it's wrong here

    Agreeing to skip User Acceptance Testing (UAT) to accommodate a sponsor's request directly increases the project's exposure to significant risks, including undetected defects, scope creep from rework, and potential user dissatisfaction. This action is not aligned with PMI-recommended practices for quality assurance and can lead to costly post-implementation issues, undermining the project's success and the PM's credibility in ensuring deliverable quality.

  • Explain the risks of skipping UAT and propose alternatives, such as reducing test scope or compressing the schedule

    Why this is correct

    The most appropriate action for a Project Manager is to proactively engage the sponsor by clearly articulating the specific risks associated with skipping UAT, such as increased defect rates, rework costs, and potential user rejection. Concurrently, the PM should propose pragmatic alternatives, like reducing the scope of UAT to focus on critical functionalities or exploring schedule compression in other areas, demonstrating a commitment to both project quality and meeting stakeholder constraints through collaborative problem-solving.

  • Escalate to the PMO or senior management that the sponsor is compromising quality

    Why it's wrong here

    Immediately escalating to the PMO or senior management that the sponsor is compromising quality is premature and can damage stakeholder relationships. A Project Manager's initial responsibility is to directly engage the sponsor, communicate the risks and implications of their request, and attempt to find a mutually agreeable solution. Escalation should be considered a last resort when direct negotiation and problem-solving efforts have demonstrably failed to resolve the conflict.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.