- A
Update the predictive baseline as approved, and coordinate with the product owner to prioritize the agile portion in the product backlog
This respects the CCB decision and uses agile flexibility for the deferred part.
- B
Implement the change for both portions since the CCB approved the overall change
Why wrong: The CCB only approved the predictive portion; the agile portion was deferred and not approved.
- C
Request the CCB to also approve the agile portion before taking any action
Why wrong: The CCB deferred the agile portion, implying it does not require their approval.
- D
Reject the change entirely because it was not fully approved
Why wrong: Partial approval means the predictive part can proceed.
Quick Answer
The correct approach is to update the predictive baseline as approved and coordinate with the product owner to prioritize the agile portion in the product backlog. This is because a partial CCB approval hybrid contract requires you to treat each lifecycle component according to its own governance rules: the predictive portion’s fixed-price contract demands a formal baseline update for the approved change, while the agile portion’s time-and-materials contract leaves prioritization to the product owner via the backlog. On the PMP exam, this scenario tests your understanding of how hybrid governance splits authority—the CCB controls predictive scope changes, but the product owner owns agile backlog decisions. A common trap is assuming the entire change must be fully approved or rejected, but the correct answer recognizes that partial approval is valid and requires parallel actions. Memory tip: “Predictive gets a baseline; Agile gets a backlog.”
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Your project is using a hybrid approach with a fixed-price contract for the predictive portion and a time-and-materials contract for the agile portion. A change request from a stakeholder would affect both portions. The change control board (CCB) has approved the change for the predictive portion but deferred the agile portion to the product owner. How should you proceed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Update the predictive baseline as approved, and coordinate with the product owner to prioritize the agile portion in the product backlog
Option C is correct because the change request impacts both portions, and the CCB has only approved part of it. The PM should update the predictive baseline and then work with the product owner to prioritize the agile portion. Option A is wrong because the CCB approval is partial. Option B ignores the approved predictive change. Option D is incorrect because the change is not fully approved.
Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Update the predictive baseline as approved, and coordinate with the product owner to prioritize the agile portion in the product backlog
Why this is correct
This respects the CCB decision and uses agile flexibility for the deferred part.
Related concept
Static NAT maps one inside address to one outside address.
- ✗
Implement the change for both portions since the CCB approved the overall change
Why it's wrong here
The CCB only approved the predictive portion; the agile portion was deferred and not approved.
- ✗
Request the CCB to also approve the agile portion before taking any action
Why it's wrong here
The CCB deferred the agile portion, implying it does not require their approval.
- ✗
Reject the change entirely because it was not fully approved
Why it's wrong here
Partial approval means the predictive part can proceed.
Common exam traps
Common exam trap: NAT rules depend on direction and matching traffic
NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.
Detailed technical explanation
How to think about this question
NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.
KKey Concepts to Remember
- Static NAT maps one inside address to one outside address.
- PAT allows many inside hosts to share one public address using ports.
- Inside local and inside global describe the private and translated addresses.
- NAT ACLs identify traffic for translation, not always security filtering.
TExam Day Tips
- Identify inside and outside interfaces first.
- Check whether the scenario needs static NAT, dynamic NAT or PAT.
- Do not confuse NAT matching ACLs with normal packet-filtering intent.
Key takeaway
NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Static NAT maps one inside address to one outside address..
What is the correct answer to this question?
The correct answer is: Update the predictive baseline as approved, and coordinate with the product owner to prioritize the agile portion in the product backlog — Option C is correct because the change request impacts both portions, and the CCB has only approved part of it. The PM should update the predictive baseline and then work with the product owner to prioritize the agile portion. Option A is wrong because the CCB approval is partial. Option B ignores the approved predictive change. Option D is incorrect because the change is not fully approved.
What should I do if I get this PMP question wrong?
Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.
What is the key concept behind this question?
Static NAT maps one inside address to one outside address.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 21, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.