Courseiva
Process — Managing Technical AspectshardMultiple SelectObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

Your project is using a hybrid approach. During a sprint review, the customer is unhappy with the progress and requests a major change in direction. This change will require significant rework and affect the project's critical path. Which THREE actions should you take?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Assess the impact of the change on scope, schedule, cost, and quality

When a major change is requested, the PM should document it as a change request, assess the impact on the project constraints, and communicate with stakeholders to manage expectations.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Assess the impact of the change on scope, schedule, cost, and quality

    Why this is correct

    Before any decision regarding a change, a thorough impact analysis is crucial. This involves evaluating how the proposed change will affect the project's scope baseline, schedule baseline, cost baseline, and quality requirements. Understanding these potential ramifications enables the project manager and stakeholders to make an informed decision, ensuring the change aligns with project objectives and constraints.

  • Instruct the team to start implementing the change immediately to satisfy the customer

    Why it's wrong here

    Instructing the team to implement a change immediately without proper evaluation and approval bypasses the established change control process. This action can lead to scope creep, budget overruns, schedule delays, and quality issues, as the implications of the change have not been formally assessed or agreed upon by all relevant stakeholders. It undermines project governance and increases project risk.

  • Document the customer's request as a formal change request

    Why this is correct

    Documenting the customer's request as a formal change request is the essential initial step in the integrated change control process. This formalization ensures the request is clearly defined, recorded, and can be properly tracked, evaluated, and managed according to the project's change management plan. It provides an official record and initiates the structured process for review and decision-making.

  • Reject the change because it was not part of the original scope

    Why it's wrong here

    Rejecting a change solely because it wasn't in the original scope without proper evaluation is a reactive and potentially detrimental approach. Project environments are dynamic, and valid changes often emerge. A project manager should facilitate the change control process to assess the change's value and impact, rather than dismissing it outright, which could lead to customer dissatisfaction or missed opportunities.

  • Communicate the impact and options to the customer and other stakeholders

    Why this is correct

    After assessing the change's impact, communicating these findings and potential options to the customer and other relevant stakeholders is paramount. This transparency ensures all parties understand the implications of proceeding with or rejecting the change, facilitates collaborative decision-making, and manages expectations effectively. Open communication fosters trust and secures necessary buy-in for the chosen path forward.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.