PMP Process — Managing Technical Aspects Practice Question
You are managing a project to build a new mobile application. An executive stakeholder has been bypassing you and giving direct instructions to team members, causing rework and confusion. What should you do first?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Schedule a meeting with the executive stakeholder to discuss the importance of following the communication plan.
The PM should address the issue directly with the stakeholder to clarify roles and communication protocols. This is a stakeholder management and communication issue that requires a proactive conversation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Send an email to all stakeholders reminding them to communicate through the project manager.
Why it's wrong here
Sending a mass email escalates the conflict publicly without first addressing the stakeholder privately, violating the PMI principle of managing stakeholder expectations through direct, respectful confrontation. This option is tempting because it enforces the formal communication protocol outlined in the communications management plan, which would be correct if the stakeholder had already ignored a private discussion about the agreed escalation path.
- ✗
Update the communications management plan to include stricter protocols.
Why it's wrong here
Unilaterally updating the communications management plan to include stricter protocols without first engaging the executive stakeholder is a premature and potentially counterproductive action. This approach fails to address the immediate behavioral issue through direct communication and risks alienating the stakeholder by imposing new rules without their input or understanding of the underlying problem. Effective project management prioritizes direct engagement to resolve deviations before resorting to formal process changes, which require stakeholder buy-in and formal change control.
- ✗
Escalate the issue to the project sponsor to intervene.
Why it's wrong here
Escalating to the sponsor bypasses the stakeholder engagement process defined in the PMBOK, which requires you first to address the stakeholder directly using your negotiation and communication management skills. This option is tempting because the sponsor holds formal authority to overrule the executive, and escalation would be correct if the stakeholder’s behaviour violated a legal or ethical boundary or if you had already attempted direct resolution without success.
- ✓
Schedule a meeting with the executive stakeholder to discuss the importance of following the communication plan.
Why this is correct
Scheduling a private meeting with the executive stakeholder is the most appropriate first step, aligning with PMP principles for managing stakeholder expectations and resolving conflicts. This direct, respectful approach allows the project manager to understand the stakeholder's perspective, reiterate the agreed-upon communication protocols, and collaboratively find a solution without public escalation or formal disciplinary action. It demonstrates proactive problem-solving and reinforces the project manager's role in maintaining effective project governance and relationships.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.