Quantitative risk analysis results
Why wrong: Incorrect: That is from quantitative analysis.
- B
Risk register updates
Correct: The risk register is updated with prioritization.
- C
Risk responses
Why wrong: Incorrect: Risk responses are from plan risk responses.
- D
List of prioritized risks
Correct: Prioritized risks are output.
- E
Probability and impact matrix
Why wrong: Incorrect: The matrix is a tool, not an output.
Quick Answer
The answer is a list of prioritized risks and risk register updates. These are the two primary outputs of qualitative risk analysis because this process evaluates the probability and impact of identified risks, then ranks them by priority for further action or monitoring. The risk register is updated with new information such as risk scores, urgency, and categorization, while the prioritized list helps the project manager focus on the most critical threats and opportunities. On the CAPM exam, this question tests your understanding of the Plan Risk Management knowledge area, specifically the difference between qualitative and quantitative analysis outputs. A common trap is confusing the prioritized risk list with the overall risk ranking from quantitative analysis, but remember that qualitative analysis uses subjective ratings, not numerical data. To recall the outputs, think of the mnemonic “PRR” — Prioritized Risks and Register updates.
CAPM Predictive Plan-Based Methodologies Practice Question
This CAPM practice question tests your understanding of predictive plan-based methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is performing qualitative risk analysis. Which TWO of the following are typical outputs of this process? (Select TWO)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Risk register updates
Qualitative risk analysis produces risk register updates and a list of prioritized risks. Options A and C are correct.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Quantitative risk analysis results
Why it's wrong here
Incorrect: That is from quantitative analysis.
- ✓
Risk register updates
Why this is correct
Correct: The risk register is updated with prioritization.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Risk responses
Why it's wrong here
Incorrect: Risk responses are from plan risk responses.
- ✓
List of prioritized risks
Why this is correct
Correct: Prioritized risks are output.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Probability and impact matrix
Why it's wrong here
Incorrect: The matrix is a tool, not an output.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Trap categories for this question
Command / output trap
Incorrect: The matrix is a tool, not an output.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Predictive Plan-Based Methodologies — study guide chapter
Learn the concepts, then practise the questions
- →
Predictive Plan-Based Methodologies practice questions
Targeted practice on this topic area only
- →
All CAPM questions
503 questions across all exam domains
- →
Certified Associate in Project Management CAPM study guide
Full concept coverage aligned to exam objectives
- →
CAPM practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related CAPM practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Agile Frameworks and Methodologies practice questions
Practise CAPM questions linked to Agile Frameworks and Methodologies.
Project Management Fundamentals and Core Concepts practice questions
Practise CAPM questions linked to Project Management Fundamentals and Core Concepts.
Predictive Plan-Based Methodologies practice questions
Practise CAPM questions linked to Predictive Plan-Based Methodologies.
Business Analysis Frameworks practice questions
Practise CAPM questions linked to Business Analysis Frameworks.
CAPM fundamentals practice questions
Practise CAPM questions linked to CAPM fundamentals.
CAPM scenario practice questions
Practise CAPM questions linked to CAPM scenario.
CAPM troubleshooting practice questions
Practise CAPM questions linked to CAPM troubleshooting.
Practice this exam
Start a free CAPM practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this CAPM question test?
Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Risk register updates — Qualitative risk analysis produces risk register updates and a list of prioritized risks. Options A and C are correct.
What should I do if I get this CAPM question wrong?
Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More CAPM practice questions
- Which THREE factors should a business analyst consider when selecting an elicitation technique for a project?
- Drag and drop the steps for conducting a procurement process in the correct order.
- Drag and drop the steps for controlling project changes according to the integrated change control process.
- Drag and drop the steps for managing project quality in the correct order.
- Drag and drop the steps for closing a project phase or project in the correct order.
- Drag and drop the steps for managing project communications in the correct order.
Last reviewed: Jun 24, 2026
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.