Question 394 of 503
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is mandatory dependency. This is correct because the relationship between foundation work and framing is governed by a physical or contractual requirement—the framing simply cannot begin until the foundation is structurally complete, making it a hard logic constraint inherent in the nature of the work. On the Certified Associate in Project Management CAPM exam, this distinction tests your ability to differentiate between dependencies that are unavoidable (mandatory) versus those that are based on team preference or best practice (discretionary). A common trap is confusing a discretionary dependency, like wanting to finish design before coding begins, with a mandatory one; remember that mandatory dependencies are often tied to legal or physical laws, not just team choice. A useful memory tip: think of mandatory as “must-do” logic—if the sequence is dictated by physics or a contract, it’s mandatory, not optional.

CAPM Predictive Plan-Based Methodologies Practice Question

This CAPM practice question tests your understanding of predictive plan-based methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is developing the project schedule for a construction project. The team has identified that the foundation work must be completed before the framing can begin. Which type of dependency does this represent?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Mandatory dependency

The dependency between foundation work and framing is a mandatory dependency because it is physically required that the foundation be completed before framing can begin. In construction, this is a hard logic constraint inherent in the nature of the work, not a preference or external factor. Mandatory dependencies are often referred to as 'hard logic' and are typically based on contractual requirements or physical limitations.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Mandatory dependency

    Why this is correct

    Mandatory dependencies are inherent in the nature of the work, such as physical or legal requirements.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Lead

    Why it's wrong here

    A lead is a schedule compression technique, not a dependency type.

  • Discretionary dependency

    Why it's wrong here

    Discretionary dependencies are based on best practices, not physical constraints.

  • External dependency

    Why it's wrong here

    External dependencies involve relationships outside the project team.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse 'mandatory dependency' with 'discretionary dependency' because they think all logical sequences are discretionary, but mandatory dependencies are those dictated by the nature of the work itself, not by preference or best practice.

Detailed technical explanation

How to think about this question

In project scheduling, mandatory dependencies are often defined by the project's contractual or physical constraints and are represented as 'finish-to-start' (FS) relationships in the precedence diagramming method (PDM). For example, in construction, concrete curing time creates a mandatory lag that cannot be shortened without compromising structural integrity. Real-world scenarios where this matters include critical path analysis, where violating a mandatory dependency would cause rework or safety hazards.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Mandatory dependency — The dependency between foundation work and framing is a mandatory dependency because it is physically required that the foundation be completed before framing can begin. In construction, this is a hard logic constraint inherent in the nature of the work, not a preference or external factor. Mandatory dependencies are often referred to as 'hard logic' and are typically based on contractual requirements or physical limitations.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More CAPM practice questions

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.