Question 1,449 of 1,731
PRINCE2 ProcesseseasyMultiple ChoiceObjective-mapped

Purpose of Starting Up a Project Process — Viability Check | PRINCE2 Foundation Explained

This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

What is the purpose of the Starting Up a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To ensure that the prerequisites for initiating the project are in place

The Starting Up a Project process is designed to ensure that the prerequisites for initiating the project are in place before the project is formally authorized. It answers the question 'Do we have a viable and worthwhile project?' by creating the Project Brief (including an outline Business Case) and appointing key roles, but it does not produce the full Business Case or Project Plan, which are developed later in the Initiating a Project process.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To ensure that the prerequisites for initiating the project are in place

    Why this is correct

    SU ensures the project is viable before moving to initiation.

    Related concept

    Read the scenario before looking for a memorised answer.

  • To close the project in a controlled manner

    Why it's wrong here

    Closing a Project (CP) is the closure process.

  • To produce the Business Case and Project Plan

    Why it's wrong here

    The Business Case is refined in IP; a plan is produced in SU (Initiation Stage Plan) but the Project Plan is in IP.

  • To initiate the project and produce the Project Initiation Documentation

    Why it's wrong here

    Initiating a Project (IP) produces the PID, not SU.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the outline Business Case created in Starting Up a Project with the full Business Case and Project Plan, which are actually developed in the Initiating a Project process.

Detailed technical explanation

How to think about this question

Under PRINCE2, the Starting Up a Project process is a pre-project activity that occurs before the project is formally initiated. It ensures that the project has a clear mandate, an executive and project manager are appointed, and an outline Business Case is created to justify the project. This process does not produce the PID; instead, it creates the Project Brief, which is later refined into the PID during the Initiating a Project process. A real-world scenario where this matters is when an organization receives a project mandate but needs to quickly assess feasibility and assign resources before committing to full initiation.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: To ensure that the prerequisites for initiating the project are in place — The Starting Up a Project process is designed to ensure that the prerequisites for initiating the project are in place before the project is formally authorized. It answers the question 'Do we have a viable and worthwhile project?' by creating the Project Brief (including an outline Business Case) and appointing key roles, but it does not produce the full Business Case or Project Plan, which are developed later in the Initiating a Project process.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

8 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. What is the purpose of the Starting Up a Project process?

easy
  • A.To check if the project is viable and worth initiating
  • B.To produce the Project Initiation Documentation
  • C.To authorize the project to proceed
  • D.To manage the delivery of products within a stage

Why A: The Starting Up a Project process ensures that there is a viable and worthwhile project before the initiation stage begins.

Variation 2. What is the purpose of the Starting Up a Project process?

easy
  • A.To manage the day-to-day activities of the project
  • B.To confirm that the project is viable and worthwhile before committing to detailed planning
  • C.To close the project in a controlled manner
  • D.To produce the Project Initiation Documentation

Why B: Option B is correct. SU is a pre-project process that ensures basic conditions exist before deciding to proceed with initiation. It does not formally start the project; that happens in IP.

Variation 3. What is the purpose of the Starting Up a Project process?

easy
  • A.To produce the Project Initiation Documentation
  • B.To authorize the closure of the project
  • C.To ensure that the prerequisites for initiating a project are in place
  • D.To manage the day-to-day delivery of products

Why C: The Starting Up a Project process ensures that the prerequisites for initiating a project are in place, such as having a Project Brief and approved initiation stage plan. It does not produce the PID or manage delivery.

Variation 4. What is the purpose of the Starting Up a Project process?

easy
  • A.To monitor the progress of the current stage
  • B.To ensure that the prerequisites for initiating a project are in place
  • C.To close the project in a controlled manner
  • D.To approve the project and authorize initiation

Why B: Starting Up a Project is a pre-project process to ensure that the project has a viable Business Case and that the necessary resources and people are in place before initiation. It does not approve, close, or monitor the project.

Variation 5. What is the purpose of the Starting Up a Project process?

easy
  • A.To check if the project is worthwhile and can be delivered
  • B.To manage the day-to-day activities of the project
  • C.To close the project in a controlled manner
  • D.To produce the Project Initiation Documentation

Why A: Starting Up a Project is a pre-project process to ensure that the project has a viable business justification and that the necessary people and resources are available before committing to the full initiation stage.

Variation 6. What is the purpose of the Starting Up a Project process?

easy
  • A.To produce the Project Initiation Documentation
  • B.To authorize the start of the project
  • C.To manage the day-to-day activities of the project
  • D.To ensure that the prerequisites for initiating a project are in place

Why D: The Starting Up a Project process is designed to ensure that the prerequisites for initiating a project are in place before any significant work begins. It focuses on verifying that the project has a viable business justification, a clear project mandate, and that necessary resources and personnel are available, thereby preventing wasted effort on projects that lack a solid foundation.

Variation 7. What is the purpose of the Starting Up a Project process?

easy
  • A.To plan the entire project in detail
  • B.To produce the Project Initiation Documentation
  • C.To ensure that there is a viable and worthwhile project before committing to a full initiation
  • D.To approve the project mandate

Why C: The Starting Up a Project process is designed to evaluate the project mandate and determine whether the project is viable and worthwhile before committing significant resources to full initiation. It ensures that the project has a clear business justification, a defined project manager, and a sufficient understanding of scope and risks to proceed. This process does not produce detailed plans or the Project Initiation Documentation (PID), which are outputs of the Initiating a Project process.

Variation 8. What is the purpose of the Starting Up a Project process?

easy
  • A.To decide whether it is worthwhile to initiate the project
  • B.To close the project in a controlled manner
  • C.To assign work packages to the Team Manager
  • D.To produce a detailed Project Plan for the entire project

Why A: The Starting Up a Project process is designed to ensure that the project has a viable business case and that all necessary pre-project activities are completed before committing to the initiation phase. Its primary purpose is to decide whether it is worthwhile to initiate the project, by evaluating the project mandate, appointing the Executive and Project Manager, and creating the Project Brief. This prevents wasted effort on projects that lack clear justification or support.

Keep practising

More PRINCE2F practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.