- A
Authorize the closure of the project
The Project Board authorizes closure in DP.
- B
Authorize an Exception Plan
The Project Board authorizes Exception Plans when tolerances are exceeded.
- C
Authorize the initiation of the project
The Project Board authorizes initiation in DP.
- D
Manage day-to-day work of the team
Why wrong: Day-to-day management is done by the Project Manager in CS.
- E
Produce the Project Plan
Why wrong: The Project Plan is produced by the Project Manager in IP.
Project Board Responsibilities in Directing a Project
This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Authorize the closure of the project
The Project Board is responsible for making key decisions and exercising overall control over the project. Authorizing closure (A) ensures the project has met its objectives and that the product has been accepted before formal closure. Authorizing an Exception Plan (B) is a board-level decision to approve a deviation from the plan when a tolerance is forecast to be exceeded. Authorizing initiation (C) gives the go-ahead for the project to proceed from the initiation stage into the detailed planning and delivery stages.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Authorize the closure of the project
Why this is correct
The Project Board authorizes closure in DP.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Authorize an Exception Plan
Why this is correct
The Project Board authorizes Exception Plans when tolerances are exceeded.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Authorize the initiation of the project
Why this is correct
The Project Board authorizes initiation in DP.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Manage day-to-day work of the team
Why it's wrong here
Day-to-day management is done by the Project Manager in CS.
- ✗
Produce the Project Plan
Why it's wrong here
The Project Plan is produced by the Project Manager in IP.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse the Project Board's strategic decision-making responsibilities with the Project Manager's operational tasks, such as managing daily work or producing plans, leading them to incorrectly select options D or E.
Detailed technical explanation
How to think about this question
In PRINCE2, the Directing a Project process covers the Project Board's decision-making from pre-project through to final closure. The board's key decisions include authorizing initiation, authorizing the project (after the Initiation Stage), authorizing stage plans, authorizing exception plans, and authorizing closure. The board does not get involved in day-to-day management or plan creation, which are delegated to the Project Manager. This separation of 'management' (board) and 'delivery' (project manager) is a core principle of PRINCE2's organizational structure.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Processes — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Processes practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Authorize the closure of the project — The Project Board is responsible for making key decisions and exercising overall control over the project. Authorizing closure (A) ensures the project has met its objectives and that the product has been accepted before formal closure. Authorizing an Exception Plan (B) is a board-level decision to approve a deviation from the plan when a tolerance is forecast to be exceeded. Authorizing initiation (C) gives the go-ahead for the project to proceed from the initiation stage into the detailed planning and delivery stages.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
6 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
hard- A.Managing risks on a daily basis
- ✓ B.Authorizing initiation of the project
- C.Preparing Highlight Reports
- ✓ D.Giving ad-hoc direction to the Project Manager
- ✓ E.Authorizing the project closure
Why B: Option B is correct because the Project Board is responsible for authorizing the initiation of the project during the Directing a Project process. This authorization formally allows the Project Manager to proceed with the Initiation Stage, committing resources and funding. It is a key decision point that ensures the project aligns with corporate or programme strategy before detailed planning begins.
Variation 2. Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
medium- ✓ A.Approving stage plans and updates
- B.Producing Checkpoint Reports
- C.Managing the day-to-day activities of the project team
- ✓ D.Authorising closure of the project
- ✓ E.Authorising initiation of the project
Why A: Option A is correct because the Project Board is responsible for approving Stage Plans and any updates to them during the Directing a Project process. This ensures that the project remains aligned with the business case and that management stage boundaries are properly controlled.
Variation 3. Which TWO of the following are responsibilities of the Project Board in the Directing a Project process?
medium- ✓ A.Authorize stage plans and give ad-hoc direction
- B.Produce Checkpoint Reports
- C.Manage day-to-day activities of the project
- ✓ D.Authorize the initiation of the project
- E.Update the Business Case
Why A: The Project Board authorizes initiation, authorizes the project, authorizes stage plans, gives ad-hoc direction, and authorizes closure. They do not manage day-to-day work or produce Checkpoint Reports.
Variation 4. Which TWO of the following are responsibilities of the Project Board in the Directing a Project process?
hard- ✓ A.Authorising project closure
- B.Managing the Business Case on a day-to-day basis
- ✓ C.Authorising project initiation
- D.Preparing the Highlight Report
- E.Appointing the Team Manager
Why A: Option A is correct because the Project Board is responsible for authorizing project closure as part of the Directing a Project process. This ensures that the project formally ends only after all objectives have been met, products accepted, and lessons recorded, providing governance and control over the project's lifecycle.
Variation 5. In the Directing a Project process, which of the following is a key responsibility of the Project Board?
easy- A.Producing Highlight Reports
- ✓ B.Authorizing the next Stage Plan
- C.Managing day-to-day work within a stage
- D.Accepting Work Packages
Why B: In PRINCE2, the Directing a Project process is the decision-making layer where the Project Board exercises overall control. A key responsibility is authorizing the next Stage Plan, which formally approves the detailed plan for the upcoming management stage and commits the resources required to execute it. This ensures the project remains viable and aligned with business justification before proceeding.
Variation 6. Which THREE of the following are responsibilities of the Project Board in the Directing a Project process?
hard- A.Producing Highlight Reports
- ✓ B.Giving ad-hoc direction to the Project Manager
- ✓ C.Authorizing the initiation of the project
- ✓ D.Authorizing the closure of the project
- E.Managing day-to-day work of the project
Why B: The Project Board is responsible for providing overall direction and control of the project. Giving ad-hoc direction to the Project Manager (Option B) is a key responsibility within the Directing a Project process, as the Board must intervene when necessary to keep the project aligned with business objectives.
Keep practising
More PRINCE2F practice questions
- Which TWO of the following statements about the Quality Review technique are correct?
- A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the…
- Which THREE of the following are PRINCE2 principles?
- A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute…
- A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What…
- Which management product is used to capture lessons during the Initiation Stage?
Last reviewed: Jun 24, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.