- A
Increase the stage budget and continue with the current plan
Why wrong: The Project Manager cannot unilaterally increase tolerances; that requires Project Board approval.
- B
Continue with the plan and report the overrun in the next Highlight Report
Why wrong: Escalation must be immediate via an Exception Report, not delayed until the next Highlight Report.
- C
Raise an Exception Report to the Project Board and await direction
This follows management by exception: the PM escalates when tolerances are forecast to be breached.
- D
Close the project immediately as the Business Case is no longer viable
Why wrong: A cost tolerance breach does not automatically mean the Business Case is unviable; the Board must assess.
Management by Exception: Cost Tolerance Breach Escalation
This PRINCE2F practice question tests your understanding of people: organizations, teams, and leadership. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Raise an Exception Report to the Project Board and await direction
Option C is correct because PRINCE2 dictates that when a project manager forecasts a deviation beyond the stage's cost tolerance, they must raise an Exception Report to the Project Board. The Project Board then decides on corrective action, such as approving a revised plan or closing the project. This ensures governance and control over the project's financial limits.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Increase the stage budget and continue with the current plan
Why it's wrong here
The Project Manager cannot unilaterally increase tolerances; that requires Project Board approval.
- ✗
Continue with the plan and report the overrun in the next Highlight Report
Why it's wrong here
Escalation must be immediate via an Exception Report, not delayed until the next Highlight Report.
- ✓
Raise an Exception Report to the Project Board and await direction
Why this is correct
This follows management by exception: the PM escalates when tolerances are forecast to be breached.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Close the project immediately as the Business Case is no longer viable
Why it's wrong here
A cost tolerance breach does not automatically mean the Business Case is unviable; the Board must assess.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse the Highlight Report (used for routine progress within tolerance) with the Exception Report (mandatory for forecast tolerance breaches), leading them to incorrectly select Option B.
Detailed technical explanation
How to think about this question
In PRINCE2, cost tolerance is a delegated authority from the Project Board to the Project Manager for a specific stage. When a forecast breach occurs, the Project Manager must immediately escalate via an Exception Report, which includes options for corrective action. The Project Board then reviews the Business Case and may approve an exception plan, which resets the stage's tolerance and plan, ensuring the project remains aligned with its justification.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People: organizations, teams, and leadership — study guide chapter
Learn the concepts, then practise the questions
- →
People: organizations, teams, and leadership practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
People: organizations, teams, and leadership — This question tests People: organizations, teams, and leadership — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Raise an Exception Report to the Project Board and await direction — Option C is correct because PRINCE2 dictates that when a project manager forecasts a deviation beyond the stage's cost tolerance, they must raise an Exception Report to the Project Board. The Project Board then decides on corrective action, such as approving a revised plan or closing the project. This ensures governance and control over the project's financial limits.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
8 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
hard- A.Continue and report the overrun in the next Highlight Report
- B.Increase the budget and continue with the current plan
- C.Close the project as the Business Case is no longer viable
- ✓ D.Raise an Exception Report to the Project Board
Why D: When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is the principle of management by exception.
Variation 2. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
medium- A.Close the project immediately
- ✓ B.Raise an Exception Report to the Project Board
- C.Increase the budget and continue with the current plan
- D.Report the overrun in the next Highlight Report
Why B: When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception.
Variation 3. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
medium- A.Close the project immediately as the Business Case is no longer viable
- B.Continue and report the cost overrun in the next Highlight Report
- ✓ C.Raise an Exception Report to the Project Board and await their direction
- D.Increase the project budget to absorb the additional cost
Why C: In PRINCE2, when a project is forecast to exceed its cost tolerance, the Project Manager must escalate the issue to the Project Board via an Exception Report. This is because the Project Manager does not have authority to exceed tolerances; the Project Board must decide whether to approve a revised Business Case, adjust tolerances, or terminate the project. Option C correctly follows the PRINCE2 principle of management by exception.
Variation 4. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
medium- ✓ A.Raise an Exception Report to the Project Board and await their direction
- B.Increase the project budget and continue with the current plan
- C.Continue with the current plan and report the overrun in the next Highlight Report
- D.Close the project immediately as the Business Case is no longer viable
Why A: In PRINCE2, when a project forecasts exceeding its cost tolerance, the Project Manager must escalate the issue to the Project Board via an Exception Report. This is a formal mechanism to request a decision on corrective action, as the Project Manager does not have authority to change tolerances or budgets. The Project Board then evaluates the situation and provides direction, ensuring governance and control over the project's viability.
Variation 5. A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
medium- A.Increase the stage budget using contingency reserves
- ✓ B.Raise an Exception Report to the Project Board
- C.Close the project as the Business Case is no longer viable
- D.Continue with the current plan and report the overrun in the next Highlight Report
Why B: According to PRINCE2's management by exception, if a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.
Variation 6. A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
medium- A.Increase the project budget to absorb the additional cost
- B.Continue and report in the next Highlight Report
- ✓ C.Raise an Exception Report to the Project Board
- D.Close the project immediately
Why C: When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report, following management by exception.
Variation 7. A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
medium- ✓ A.Raise an Exception Report to the Project Board
- B.Increase the budget and continue
- C.Close the project immediately
- D.Continue and report in the next Highlight Report
Why A: Escalation via Exception Report is required when a tolerance is forecast to be exceeded.
Variation 8. A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
medium- A.Report the overrun in the next Highlight Report
- ✓ B.Raise an Exception Report to the Project Board
- C.Close the project as the Business Case is no longer viable
- D.Increase the stage budget and continue
Why B: In PRINCE2, when a project manager forecasts that a stage will exceed its cost tolerance, they must escalate the issue to the Project Board by raising an Exception Report. This is because tolerances are delegated limits, and exceeding them requires board-level decision-making, not just reporting or self-authorization. The Exception Report triggers an Exception Plan to recover or adjust the project.
Keep practising
More PRINCE2F practice questions
- Which TWO of the following statements about the Quality Review technique are correct?
- A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the…
- Which THREE of the following are PRINCE2 principles?
- A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute…
- A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What…
- Which management product is used to capture lessons during the Initiation Stage?
Last reviewed: Jun 24, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.