- A
Report highlights to the Project Board
Highlight Reports are sent to the Project Board during CS.
- B
Produce End Stage Report
Why wrong: End Stage Report is produced in Managing a Stage Boundary.
- C
Deliver work packages
Why wrong: Delivering work packages is done in Managing Product Delivery.
- D
Authorize Work Packages
The PM authorizes Work Packages in CS.
- E
Review progress and update the stage plan
Regular review of progress is part of CS.
Controlling a Stage Process — Key Activities & Traps
This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which THREE of the following are activities performed in the Controlling a Stage process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Report highlights to the Project Board
Option A is correct because reporting highlights to the Project Board is a key activity in the Controlling a Stage process. This process ensures that the project manager keeps the board informed of progress against the stage plan, including any issues or risks, so that the board can provide continued direction and control.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Report highlights to the Project Board
Why this is correct
Highlight Reports are sent to the Project Board during CS.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Produce End Stage Report
Why it's wrong here
End Stage Report is produced in Managing a Stage Boundary.
- ✗
Deliver work packages
Why it's wrong here
Delivering work packages is done in Managing Product Delivery.
- ✓
Authorize Work Packages
Why this is correct
The PM authorizes Work Packages in CS.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Review progress and update the stage plan
Why this is correct
Regular review of progress is part of CS.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse the activities of the Controlling a Stage process with those of the Managing a Stage Boundary process, particularly the production of the End Stage Report, which is a boundary activity, not a control activity.
Detailed technical explanation
How to think about this question
The Controlling a Stage process focuses on the day-to-day management of the stage, including authorizing work packages, reviewing progress, and reporting highlights. The project manager uses the stage plan as a baseline to monitor actual progress against planned work, and any deviations trigger corrective actions or escalation to the Project Board. This process ensures that the stage remains within tolerance and that the board retains control through regular highlight reports.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Processes — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Processes practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Report highlights to the Project Board — Option A is correct because reporting highlights to the Project Board is a key activity in the Controlling a Stage process. This process ensures that the project manager keeps the board informed of progress against the stage plan, including any issues or risks, so that the board can provide continued direction and control.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
6 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which TWO of the following are activities performed during the Controlling a Stage process?
medium- A.Produce the Project Initiation Documentation
- ✓ B.Review the Business Case
- C.Produce the End Project Report
- D.Appoint the Executive
- ✓ E.Authorize Work Packages
Why B: CS includes authorizing Work Packages, reviewing progress, and reporting. Producing the PID is done in IP.
Variation 2. Which THREE of the following are activities performed during the Controlling a Stage process?
medium- ✓ A.Authorise Work Packages
- B.Produce the End Stage Report
- C.Produce the Project Plan
- ✓ D.Report on progress to the Project Board via Highlight Reports
- ✓ E.Take corrective action to keep the stage within tolerance
Why A: CS includes authorising Work Packages, reviewing progress, reporting highlights, and managing issues and risks.
Variation 3. Which THREE of the following are activities performed during the Controlling a Stage process?
hard- ✓ A.Review progress against the Stage Plan
- B.Produce the Project Plan
- C.Produce the End Stage Report
- ✓ D.Authorize Work Packages
- ✓ E.Manage issues and risks
Why A: Authorizing Work Packages, reviewing progress, and managing risks and issues are key activities of Controlling a Stage. Producing the End Stage Report is done in Managing a Stage Boundary, and producing the Project Plan is done in Initiating a Project.
Variation 4. Which THREE of the following are activities performed during the Controlling a Stage process?
hard- A.Authorize the project
- B.Plan the next stage
- ✓ C.Review the stage status
- ✓ D.Authorize a Work Package
- ✓ E.Escalate issues to the Project Board
Why C: CS includes authorizing Work Packages, reviewing progress, and escalating issues. Planning the next stage is done in Managing a Stage Boundary. Authorizing the project is done in Directing a Project.
Variation 5. Which THREE of the following are activities performed in the Controlling a Stage process?
hard- A.Create the Project Plan
- ✓ B.Review progress against the Stage Plan
- ✓ C.Authorize Work Packages
- D.Close the project
- ✓ E.Escalate issues and risks to the Project Board
Why B: CS includes activities like authorizing Work Packages, managing issues, and reviewing progress. Closing the project is CP; creating the Project Plan is IP.
Variation 6. Which THREE activities are part of the Controlling a Stage process?
hard- ✓ A.Authorize Work Packages
- B.Produce the Project Initiation Documentation (PID)
- ✓ C.Review progress and update stage status
- D.Approve the next Stage Plan
- ✓ E.Escalate issues and risks that exceed stage tolerances
Why A: Authorizing Work Packages, reviewing progress, and escalating exceptions are all activities in CS. Producing the PID is done in IP. Approving the next Stage Plan is done by the Project Board in DP.
Keep practising
More PRINCE2F practice questions
- Which TWO of the following statements about the Quality Review technique are correct?
- A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the…
- Which THREE of the following are PRINCE2 principles?
- A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute…
- A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What…
- Which management product is used to capture lessons during the Initiation Stage?
Last reviewed: Jul 4, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.