Question 495 of 503
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is three work packages at WBS level 2. In a Work Breakdown Structure, each descending level represents an increasingly detailed decomposition of project work, and level 2 directly follows the top-level project node (level 1). Here, the second level contains the three major deliverables: Planning, Execution, and Closure, which are the primary work packages at that tier. On the CAPM exam, this tests your ability to distinguish between WBS levels and avoid confusing work packages with summary tasks or leaf nodes—a common trap is counting the lowest-level items (like the six leaf nodes) instead of the components at the specified level. To remember this, think of level 2 as the “big three” phases that break down the project’s life cycle; if the question asks for a specific level, count only the items directly under that level’s parent, not the final deliverables. A helpful mnemonic is “Level 2: the trio of phases you can see.”

CAPM Predictive Plan-Based Methodologies Practice Question

This CAPM practice question tests your understanding of predictive plan-based methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Refer to the exhibit.
```json
{
  "WBS": {
    "1.0 Project": {
      "1.1 Planning": {
        "1.1.1 Requirements",
        "1.1.2 Design"
      },
      "1.2 Execution": {
        "1.2.1 Development",
        "1.2.2 Testing"
      },
      "1.3 Closure": {
        "1.3.1 Deployment",
        "1.3.2 Handover"
      }
    }
  }
}
```

How many work packages are at WBS level 2 (the second level) in this exhibit?

Question 1mediummultiple choice
Full question →

Exhibit

Refer to the exhibit.
```json
{
  "WBS": {
    "1.0 Project": {
      "1.1 Planning": {
        "1.1.1 Requirements",
        "1.1.2 Design"
      },
      "1.2 Execution": {
        "1.2.1 Development",
        "1.2.2 Testing"
      },
      "1.3 Closure": {
        "1.3.1 Deployment",
        "1.3.2 Handover"
      }
    }
  }
}
```

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

3

Option C is correct. Level 1 is '1.0 Project'. Level 2 consists of '1.1 Planning', '1.2 Execution', and '1.3 Closure' — that's three work packages. Option A counts only two, option B counts four incorrectly, option D counts six (the leaf nodes).

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 3

    Why this is correct

    The three decomposition elements at level 2 are Planning, Execution, and Closure.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 4

    Why it's wrong here

    This would count the sub-elements at level 3, not level 2.

  • 2

    Why it's wrong here

    There are more than two elements at level 2.

  • 6

    Why it's wrong here

    This counts all leaf work packages, which are at level 3, not level 2.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 3 — Option C is correct. Level 1 is '1.0 Project'. Level 2 consists of '1.1 Planning', '1.2 Execution', and '1.3 Closure' — that's three work packages. Option A counts only two, option B counts four incorrectly, option D counts six (the leaf nodes).

What should I do if I get this CAPM question wrong?

Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More CAPM practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.