- A
Reject the module and request the vendor to correct it according to the original criteria
Why wrong: This may be valid, but first you should analyze the impact and consider alternatives through change control.
- B
Escalate to the project sponsor for a decision on whether to accept the module
Why wrong: The project manager should handle this via change control, not bypass to sponsor.
- C
Accept the team member's suggestion to avoid the delay, but document the deviation
Why wrong: Accepting non-conforming deliverables without formal change approval is unacceptable.
- D
Initiate a change request to formally evaluate the impact of modifying the acceptance criteria
Following the change control process ensures all impacts are assessed before deciding.
Quick Answer
The correct action is to initiate a change request to formally evaluate the impact of modifying the acceptance criteria. This is required because the project management plan and the procurement statement of work are baselined documents; any deviation from them, such as accepting a vendor deliverable non-conformance without analysis, constitutes uncontrolled scope creep. The proper vendor deliverable non conformance change control process ensures that the impact on cost, schedule, and quality is assessed before any decision is made. On the Certified Associate in Project Management CAPM exam, this scenario tests your understanding that the change control system is the only authorized path for altering baselines, even when a delay is threatened. A common trap is choosing to accept the module to save time, which bypasses formal governance. Remember the mnemonic “CR before CR” — always submit a Change Request before you Change the Requirements.
CAPM Practice Question: Project Management Fundamentals and Core Concepts
This CAPM practice question tests your understanding of project management fundamentals and core concepts. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
You are managing a project to implement a new customer relationship management (CRM) system. The project management plan has been approved, and you are in the executing process group. A team member reports that a vendor has delivered a software module that does not meet the acceptance criteria specified in the procurement statement of work. The team member suggests modifying the acceptance criteria to accept the module as is, because returning it would cause a two-week delay. You review the project management plan and the requirements documentation. What should you do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Initiate a change request to formally evaluate the impact of modifying the acceptance criteria
Changing acceptance criteria without formal change control is scope creep and violates the project management plan. The correct action is to follow the change control process to evaluate the impact. Option A is incorrect because it bypasses control. Option B is premature without analysis. Option C is too harsh without understanding the issue.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reject the module and request the vendor to correct it according to the original criteria
Why it's wrong here
This may be valid, but first you should analyze the impact and consider alternatives through change control.
- ✗
Escalate to the project sponsor for a decision on whether to accept the module
Why it's wrong here
The project manager should handle this via change control, not bypass to sponsor.
- ✗
Accept the team member's suggestion to avoid the delay, but document the deviation
Why it's wrong here
Accepting non-conforming deliverables without formal change approval is unacceptable.
- ✓
Initiate a change request to formally evaluate the impact of modifying the acceptance criteria
Why this is correct
Following the change control process ensures all impacts are assessed before deciding.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Project Management Fundamentals and Core Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Fundamentals and Core Concepts practice questions
Targeted practice on this topic area only
- →
All CAPM questions
503 questions across all exam domains
- →
Certified Associate in Project Management CAPM study guide
Full concept coverage aligned to exam objectives
- →
CAPM practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related CAPM practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Agile Frameworks and Methodologies practice questions
Practise CAPM questions linked to Agile Frameworks and Methodologies.
Project Management Fundamentals and Core Concepts practice questions
Practise CAPM questions linked to Project Management Fundamentals and Core Concepts.
Predictive Plan-Based Methodologies practice questions
Practise CAPM questions linked to Predictive Plan-Based Methodologies.
Business Analysis Frameworks practice questions
Practise CAPM questions linked to Business Analysis Frameworks.
CAPM fundamentals practice questions
Practise CAPM questions linked to CAPM fundamentals.
CAPM scenario practice questions
Practise CAPM questions linked to CAPM scenario.
CAPM troubleshooting practice questions
Practise CAPM questions linked to CAPM troubleshooting.
Practice this exam
Start a free CAPM practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this CAPM question test?
Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Initiate a change request to formally evaluate the impact of modifying the acceptance criteria — Changing acceptance criteria without formal change control is scope creep and violates the project management plan. The correct action is to follow the change control process to evaluate the impact. Option A is incorrect because it bypasses control. Option B is premature without analysis. Option C is too harsh without understanding the issue.
What should I do if I get this CAPM question wrong?
Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More CAPM practice questions
- Which THREE factors should a business analyst consider when selecting an elicitation technique for a project?
- Drag and drop the steps for conducting a procurement process in the correct order.
- Drag and drop the steps for controlling project changes according to the integrated change control process.
- Drag and drop the steps for managing project quality in the correct order.
- Drag and drop the steps for closing a project phase or project in the correct order.
- Drag and drop the steps for managing project communications in the correct order.
Last reviewed: Jun 24, 2026
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.