Question 354 of 503
Project Management Fundamentals and Core ConceptsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is 1 day. This is correct because total float calculation measures how long a task can be delayed without affecting the overall project finish date, and it is found by subtracting the duration of the path containing the task from the critical path duration. Here, Task B lies on the non-critical path A-B-D-E, which totals 6 days, while the critical path A-C-E is 7 days, so 7 minus 6 equals 1 day of float. On the CAPM exam, this concept tests your ability to identify the critical path and compute schedule flexibility, often appearing in network diagram questions where a common trap is confusing total float with free float or assuming all tasks on non-critical paths have the same float. A reliable memory tip is to think of total float as the “slack” a task has before it becomes critical—just remember: critical path minus your path equals your float.

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Refer to the exhibit.

Task A: duration 5 days, predecessor: none
Task B: duration 3 days, predecessor: A
Task C: duration 4 days, predecessor: A
Task D: duration 2 days, predecessor: B, C

Refer to the exhibit. What is the total float of Task B?

Question 1mediummultiple choice
Full question →

Exhibit

Refer to the exhibit.

Task A: duration 5 days, predecessor: none
Task B: duration 3 days, predecessor: A
Task C: duration 4 days, predecessor: A
Task D: duration 2 days, predecessor: B, C

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

1 day

Task B has a total float of 1 day because it lies on a non-critical path. The critical path (A-C-E) has a duration of 7 days, while the path containing Task B (A-B-D-E) has a duration of 6 days. Total float is calculated as the difference between the duration of the critical path and the duration of the path containing the task, which is 7 - 6 = 1 day.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 1 day

    Why this is correct

    The critical path is A-C-D (11 days). Path A-B-D is 10 days, so float = 1 day.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 3 days

    Why it's wrong here

    This is the duration of Task B, not its float.

  • 2 days

    Why it's wrong here

    The difference in path durations is 1 day.

  • 0 days

    Why it's wrong here

    Task B is not on the critical path.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often mistakenly assume all tasks with dependencies have zero float, or they incorrectly calculate the path duration by omitting a task or misreading the diagram, leading them to pick 0 days or an inflated float value.

Detailed technical explanation

How to think about this question

Total float (also called slack) is the amount of time a task can be delayed without affecting the project finish date. It is computed using the forward and backward pass: Total Float = Late Start - Early Start (or Late Finish - Early Finish). In this network diagram, the critical path is determined by the longest sequence of dependent tasks, and any task not on that path has positive float. Real-world project managers use float to prioritize resources and manage schedule risk, as tasks with zero float require strict monitoring.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 1 day — Task B has a total float of 1 day because it lies on a non-critical path. The critical path (A-C-E) has a duration of 7 days, while the path containing Task B (A-B-D-E) has a duration of 6 days. Total float is calculated as the difference between the duration of the critical path and the duration of the path containing the task, which is 7 - 6 = 1 day.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More CAPM practice questions

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.