Courseiva
Predictive Plan-Based MethodologiesmediumMatchingObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

Match each project management methodology to its characteristic.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Sequential phases with little iteration

Iterative and incremental delivery

Time-boxed sprints with daily standups

Visual workflow with WIP limits

Process-based with defined roles

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Waterfall: Sequential phases with distinct stages such as requirements, design, implementation, testing, and deployment.

Waterfall uses sequential phases; Agile is iterative and flexible; Scrum is an Agile framework with sprints; Kanban visualizes workflow with WIP limits. Common confusions: swapping Kanban with Agile, or describing Waterfall as iterative.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Waterfall: Sequential phases with distinct stages such as requirements, design, implementation, testing, and deployment.

    Why this is correct

    Waterfall is a linear sequential model where each phase must be completed before moving to the next.

  • Agile: Visual management of work in progress with limits on simultaneous tasks.

    Why it's wrong here

    This describes Kanban, not Agile. Agile is an iterative approach emphasizing flexibility and customer feedback.

  • Scrum: A framework using fixed-length sprints, daily stand-ups, and defined roles like Scrum Master and Product Owner.

    Why this is correct

    Scrum is an Agile framework that organizes work into sprints and includes ceremonies and roles.

  • Kanban: A pull-based system focused on visualizing workflow, limiting work in progress, and managing flow.

    Why this is correct

    Kanban uses a board to visualize tasks and limits WIP to improve efficiency.

  • Agile: Iterative development with frequent delivery of small increments and continuous customer involvement.

    Why this is correct

    Agile promotes iterative cycles, adaptive planning, and collaboration with stakeholders.

  • Waterfall: Iterative cycles with frequent reassessment and adaptation.

    Why it's wrong here

    Incorrect — Waterfall is not iterative; this describes Agile or other iterative methodologies.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.