Courseiva
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

During project planning, the team identifies that a task has a duration of 10 days, a predecessor finish-to-start relationship, and a lag of 2 days. What is the earliest the successor task can start if the predecessor starts on day 1?

⚠ Common exam trap

The trap here is that candidates often forget to include the predecessor's full duration when calculating the successor's start, mistakenly adding the lag to the start date instead of the finish date, leading to an answer like day 3 or day 12.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Day 12

The predecessor starts on day 1 and has a duration of 10 days, so its early finish is day 10 (assuming no gaps). With a finish-to-start relationship and a lag of 2 days, the successor's early start is the predecessor's early finish plus the lag: 10 + 2 = 12. Therefore, the earliest the successor can start is day 12.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Day 11

    Why it's wrong here

    Day 11: This would be the case if the lag were 1 day instead of 2, or if you incorrectly added only 1 day after the finish.

  • Day 10

    Why it's wrong here

    Day 10: This would be the case if there were no lag and the successor could start immediately after the predecessor finishes.

  • Day 12

    Why this is correct

    Day 12: Correct, as calculated by adding the lag to the predecessor's finish date.

  • Day 13

    Why it's wrong here

    Day 13: This is a common mistake where candidates add the lag to the start date (1 + 10 + 2 = 13) instead of the finish date, or they misinterpret the finish day.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.