Question 61 of 503
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is day 13. This is correct because in a finish-to-start relationship with lag, the successor task cannot begin until the predecessor has fully completed and the specified lag period has elapsed. Since the predecessor starts on day 1 and has a 10-day duration, it finishes at the end of day 10; adding the 2-day lag means the successor’s earliest start is the beginning of day 13. On the CAPM exam, schedule network analysis with lag tests your ability to apply logical dependencies and time buffers correctly, often using a finish-to-start relationship as the most common type. A frequent trap is forgetting to count the lag after the predecessor’s finish, or mistakenly adding the lag to the start date instead of the finish date. Remember the mnemonic: “Finish first, then lag, then start” — always calculate the predecessor’s end date before adding any lag to find the successor’s earliest start.

CAPM Predictive Plan-Based Methodologies Practice Question

This CAPM practice question tests your understanding of predictive plan-based methodologies. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During project planning, the team identifies that a task has a duration of 10 days, a predecessor finish-to-start relationship, and a lag of 2 days. What is the earliest the successor task can start if the predecessor starts on day 1?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Day 12

The predecessor starts on day 1 and has a duration of 10 days, so it finishes at the end of day 10 (assuming work starts at the beginning of day 1). With a finish-to-start relationship and a lag of 2 days, the successor cannot start until 2 days after the predecessor finishes. Therefore, the earliest start for the successor is day 13 (end of day 10 + 2 days lag = start of day 13). Option C is correct because it accounts for both the full duration and the lag.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Day 11

    Why it's wrong here

    Assumes start on day 1 finish? Wrong.

  • Day 10

    Why it's wrong here

    Ignores lag.

  • Day 12

    Why this is correct

    Correct calculation.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Day 13

    Why it's wrong here

    Incorrect.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often forget to include the predecessor's full duration when calculating the successor's start, mistakenly adding the lag to the start date instead of the finish date, leading to an answer like day 3 or day 12.

Detailed technical explanation

How to think about this question

In project scheduling, a finish-to-start (FS) relationship with lag means the successor's start is delayed by the lag duration after the predecessor's finish. The calculation is: predecessor start + predecessor duration + lag = earliest successor start. Here, day 1 start + 10 days duration = finish at end of day 10; adding 2 days lag means the successor starts at the beginning of day 13. This is critical in critical path method (CPM) analysis, where miscomputing lag can shift the entire project timeline.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Day 12 — The predecessor starts on day 1 and has a duration of 10 days, so it finishes at the end of day 10 (assuming work starts at the beginning of day 1). With a finish-to-start relationship and a lag of 2 days, the successor cannot start until 2 days after the predecessor finishes. Therefore, the earliest start for the successor is day 13 (end of day 10 + 2 days lag = start of day 13). Option C is correct because it accounts for both the full duration and the lag.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.