CAPM Predictive Plan-Based Methodologies Practice Question
Exhibit
Refer to the exhibit. Exhibit: ``` WBS Dictionary Entry: WBS ID: 1.2.3 Work Package: Install network cabling Description: Run Cat6 cables from server room to all workstations. Responsible: IT Infrastructure Team Duration: 10 days Cost: $15,000 Acceptance Criteria: All cables tested and certified. ```
Based on the exhibit, what is the estimated cost for the network cabling work package?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
$15,000
The WBS dictionary shows Cost: $15,000. Options A, C, and D are incorrect because they do not match the WBS dictionary.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
$20,000
Why it's wrong here
Exceeds the stated cost.
- ✓
$15,000
Why this is correct
The dictionary explicitly states $15,000.
- ✗
$12,000
Why it's wrong here
Not supported by the WBS dictionary.
- ✗
$10,000
Why it's wrong here
This is the duration in days, not cost.
Go deeper
Related to this question
About these practice questions
This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.