Question 485 of 503
Predictive Plan-Based MethodologieshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is three-point estimating, the correct technique for accounting for uncertainty in activity duration estimates. This method explicitly addresses risk by calculating a weighted or simple average of three distinct estimates: the optimistic (best-case), most likely (realistic), and pessimistic (worst-case) durations. For a project involving new technology that could cause delays, the pessimistic estimate captures that potential risk range, making it ideal for modeling uncertainty through either a triangular or PERT (beta) distribution. On the CAPM exam, this question tests your understanding of the Estimate Activity Durations process in the Schedule Management knowledge area, often appearing as a scenario where historical data exists but new variables introduce unknowns. A common trap is choosing analogous estimating, which relies on past projects without adjusting for novel risks, or parametric estimating, which uses statistical relationships but not explicit uncertainty ranges. To remember this, think of the three-point estimating as your “three-sided safety net” for uncertainty: optimistic, most likely, and pessimistic cover all possible outcomes.

CAPM Predictive Plan-Based Methodologies Practice Question

This CAPM practice question tests your understanding of predictive plan-based methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is estimating activity durations for a software development project. The team has historical data from similar projects, but the current project involves new technology that could cause delays. Which estimating technique should the project manager use to account for uncertainty?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Three-point estimating

Three-point estimating (C) is correct because it explicitly accounts for uncertainty by using optimistic, most likely, and pessimistic estimates. The new technology introduces unknown risks, making the triangular or PERT distribution ideal for modeling the potential delay range.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Parametric estimating

    Why it's wrong here

    Uses statistical relationships, not uncertainty ranges.

  • Analogous estimating

    Why it's wrong here

    Uses similar projects, less accurate.

  • Three-point estimating

    Why this is correct

    Incorporates uncertainty via three values.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Bottom-up estimating

    Why it's wrong here

    Detailed but does not handle uncertainty explicitly.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often choose analogous estimating (B) because it seems quick and uses past data, but they miss that new technology invalidates the similarity assumption, making three-point estimating the correct choice for uncertainty.

Trap categories for this question

  • Similar concept trap

    Uses similar projects, less accurate.

Detailed technical explanation

How to think about this question

Three-point estimating uses the formula (O + 4M + P)/6 for PERT (Program Evaluation and Review Technique) or (O + M + P)/3 for triangular distribution, where O is optimistic, M is most likely, and P is pessimistic. In practice, the project manager would consult developers to define the pessimistic duration based on known risks of the new technology (e.g., integration delays, learning curve), ensuring the schedule buffer reflects realistic uncertainty.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Three-point estimating — Three-point estimating (C) is correct because it explicitly accounts for uncertainty by using optimistic, most likely, and pessimistic estimates. The new technology introduces unknown risks, making the triangular or PERT distribution ideal for modeling the potential delay range.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More CAPM practice questions

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.