The correct answer is the risk management plan, along with the scope management plan and schedule management plan, as these are all subsidiary plans that form part of the project management plan. The key technical distinction is that the project management plan is the master document defining how the project is executed, monitored, and controlled, containing only formal management plans and baselines, whereas project documents like the issue log and stakeholder register are supporting inputs and outputs used to inform the plan but are not part of it. On the CAPM exam, this question tests your understanding of the Project Integration Management knowledge area and the difference between the plan itself and the documents that feed into it; a common trap is confusing a subsidiary plan (e.g., risk management plan) with a project document (e.g., risk register). To remember, think of the project management plan as the “how-to” blueprint for the entire project, while project documents are the “what” and “who” details that support it. A useful memory tip is “Plans are part of the PMP; logs and registers are just documents.”

CAPM Predictive Plan-Based Methodologies Practice Question

This CAPM practice question tests your understanding of predictive plan-based methodologies. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which THREE of the following are typically included in a project management plan (as opposed to project documents)?

Question 1easymulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule management plan

Options A, C, and E are correct. The scope management plan, schedule management plan, and risk management plan are subsidiary plans of the project management plan. Option B is wrong because the issue log is a project document. Option D is wrong because the stakeholder register is a project document.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Schedule management plan

    Why this is correct

    It describes how the schedule will be managed.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Scope management plan

    Why this is correct

    It is a component of the project management plan.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Stakeholder register

    Why it's wrong here

    The stakeholder register is a project document.

  • Risk management plan

    Why this is correct

    It outlines risk management processes.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Issue log

    Why it's wrong here

    The issue log is a project document, not a part of the plan.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Schedule management plan — Options A, C, and E are correct. The scope management plan, schedule management plan, and risk management plan are subsidiary plans of the project management plan. Option B is wrong because the issue log is a project document. Option D is wrong because the stakeholder register is a project document.

What should I do if I get this CAPM question wrong?

Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More CAPM practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.