Question 441 of 503

Quick Answer

The correct answer is that the project is over budget but ahead of schedule. This conclusion comes directly from interpreting CPI and SPI values in earned value management: a CPI of 0.8 means for every dollar spent, only $0.80 of work is earned, signaling a cost overrun, while an SPI of 1.1 means $1.10 of work is earned for every dollar of planned work, indicating the project is ahead of schedule. On the CAPM exam, this question tests your ability to quickly read these indices without calculation—a common trap is confusing the direction of the values, such as thinking a CPI below 1.0 is good. Remember the memory tip: “CPI under 1, cost underdone; SPI over 1, schedule overrun” (or for this case, SPI over 1 means schedule ahead).

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. Compare every option against the stated constraints before choosing — the best answer satisfies all requirements, not just the most obvious one. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is assigned to a project that is in execution phase. The project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. Which of the following best describes the current status of the project?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "best"

    Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget but ahead of schedule.

A CPI of 0.8 means the project is earning only $0.80 for every $1.00 spent, indicating it is over budget. An SPI of 1.1 means the project is earning $1.10 for every $1.00 of planned work, indicating it is ahead of schedule. Therefore, the project is over budget but ahead of schedule, making option C correct.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is under budget and ahead of schedule.

    Why it's wrong here

    CPI < 1 means over budget, not under.

  • The project is under budget and behind schedule.

    Why it's wrong here

    Both indices are opposite of this statement.

  • The project is over budget but ahead of schedule.

    Why this is correct

    CPI=0.8 (<1) indicates cost overrun; SPI=1.1 (>1) indicates ahead of schedule.

    Clue confirmation

    The clue word "best" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The project is over budget and behind schedule.

    Why it's wrong here

    SPI > 1 means ahead of schedule, not behind.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the direction of the indices, incorrectly assuming a CPI less than 1 means under budget or an SPI greater than 1 means behind schedule, when in fact CPI < 1 indicates over budget and SPI > 1 indicates ahead of schedule.

Detailed technical explanation

How to think about this question

CPI and SPI are derived from Earned Value Management (EVM) calculations: CPI = EV/AC and SPI = EV/PV. A CPI of 0.8 means the cost variance (CV = EV - AC) is negative, indicating cost overrun. An SPI of 1.1 means the schedule variance (SV = EV - PV) is positive, indicating the project is ahead of schedule. In practice, a project can be ahead of schedule but over budget if tasks are being completed faster than planned but at a higher cost, such as due to overtime or expedited shipping.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The project is over budget but ahead of schedule. — A CPI of 0.8 means the project is earning only $0.80 for every $1.00 spent, indicating it is over budget. An SPI of 1.1 means the project is earning $1.10 for every $1.00 of planned work, indicating it is ahead of schedule. Therefore, the project is over budget but ahead of schedule, making option C correct.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More CAPM practice questions

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.