Question 887 of 1,731
PRINCE2 PracticeseasyMultiple ChoiceObjective-mapped

Quick Answer

The answer is the Project Manager, who is responsible for maintaining the Business Case throughout the project. This is correct because PRINCE2 defines the Business Case as a living document that must be continuously reviewed and updated to reflect actual costs, benefits, and risks, ensuring the project remains viable against its original justification. The Project Manager performs this ongoing maintenance, monitoring deviations and escalating any loss of viability to the Project Board for a decision. On the PRINCE2 Foundation exam, this question tests your understanding of the Project Manager’s day-to-day responsibilities versus the Project Board’s approval authority; a common trap is confusing the Project Manager’s maintenance role with the Senior User or Executive, who only provide input or approve changes. To remember this, think: the Manager manages the case, the Board decides its fate.

PRINCE2F PRINCE2 Practices Practice Question

This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

According to PRINCE2, who is responsible for maintaining the Business Case throughout the project?

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project. This includes monitoring the project's viability against the Business Case, updating it with actual costs and benefits, and escalating any deviations to the Project Board. The Project Manager ensures the Business Case remains a living document that reflects the current justification for the project.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why this is correct

    Correct. The Project Manager maintains the Business Case.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Senior Supplier

    Why it's wrong here

    The Senior Supplier represents the supplier side.

  • Senior User

    Why it's wrong here

    The Senior User represents the users, not the Business Case.

  • Project Board

    Why it's wrong here

    The Project Board collectively owns the Business Case, but the Project Manager maintains it.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often assume the Project Board, as the ultimate decision-making body, is responsible for maintaining the Business Case, but PRINCE2 explicitly assigns this maintenance role to the Project Manager.

Detailed technical explanation

How to think about this question

The Business Case is a key PRINCE2 management product that is developed during the Starting Up a Project process and maintained throughout the project. The Project Manager uses it to assess whether the project remains viable, comparing planned vs actual costs and benefits. If the Business Case shows the project is no longer justified, the Project Manager must escalate to the Project Board for a decision on whether to continue.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Project Manager — In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project. This includes monitoring the project's viability against the Business Case, updating it with actual costs and benefits, and escalating any deviations to the Project Board. The Project Manager ensures the Business Case remains a living document that reflects the current justification for the project.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. According to PRINCE2, who is responsible for maintaining the Business Case throughout the project?

easy
  • A.The Executive
  • B.The Project Manager
  • C.The Project Assurance
  • D.The Senior User

Why B: The Project Manager is responsible for maintaining the Business Case (keeping it up to date), while the Executive owns it and is accountable for its justification.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.