- A
Ask the Project Board for more tolerance
Why wrong: Formal escalation via Exception Report is required first.
- B
Close the project
Why wrong: Closing the project is a decision for the Project Board.
- C
Continue with the current plan and report in the next Highlight Report
Why wrong: Escalation is immediate, not delayed.
- D
Raise an Exception Report to the Project Board
Correct. Escalate via Exception Report.
Quick Answer
The answer is to raise an Exception Report to the Project Board. This is correct because PRINCE2 mandates management by exception, meaning the Project Manager is only empowered to work within agreed tolerances; when a forecast shows the cost tolerance will be exceeded, the manager must immediately escalate the issue rather than attempting corrective action independently. The Exception Report triggers a formal decision from the Project Board, who can authorize a new plan or adjust tolerances, ensuring governance is maintained. On the PRINCE2 Foundation exam, this question tests your understanding of the escalation chain and the precise role of tolerances in delegated authority. A common trap is confusing an Exception Report with a Highlight Report or assuming the manager should fix the problem first—remember, the manager manages within tolerance, not beyond it. Memory tip: think of an Exception Report as the “red flag” you wave when the budget line is breached, forcing the board to steer the ship.
PRINCE2F PRINCE2 Practices Practice Question
This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project is forecast to exceed its cost tolerance. What should the Project Manager do first?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Raise an Exception Report to the Project Board
D is correct because PRINCE2 requires the Project Manager to escalate any forecast deviation beyond tolerance to the Project Board via an Exception Report. This triggers a formal decision process, ensuring the board can authorize corrective action before the situation worsens.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Ask the Project Board for more tolerance
Why it's wrong here
Formal escalation via Exception Report is required first.
- ✗
Close the project
Why it's wrong here
Closing the project is a decision for the Project Board.
- ✗
Continue with the current plan and report in the next Highlight Report
Why it's wrong here
Escalation is immediate, not delayed.
- ✓
Raise an Exception Report to the Project Board
Why this is correct
Correct. Escalate via Exception Report.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may think the Project Manager can simply request more tolerance or continue reporting normally, failing to recognize that PRINCE2 mandates immediate escalation via an Exception Report when tolerance is forecast to be exceeded.
Detailed technical explanation
How to think about this question
In PRINCE2, tolerance is a delegated authority limit set by the Project Board; exceeding it requires an Exception Report, which includes the impact, options, and a recommendation. The board then decides whether to revise tolerance, approve a corrective plan, or close the project. This mechanism ensures that the Project Manager does not unilaterally exceed delegated authority, maintaining control at the appropriate management level.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Practices — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Practices practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Raise an Exception Report to the Project Board — D is correct because PRINCE2 requires the Project Manager to escalate any forecast deviation beyond tolerance to the Project Board via an Exception Report. This triggers a formal decision process, ensuring the board can authorize corrective action before the situation worsens.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
8 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
medium- A.Continue with the current plan and report the cost overrun in the next Highlight Report
- ✓ B.Raise an Exception Report to the Project Board and await their direction
- C.Increase the project budget to absorb the additional cost and continue with the current plan
- D.Close the project immediately as the Business Case is no longer viable
Why B: When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception.
Variation 2. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
hard- A.Close the project as the Business Case is no longer viable
- B.Continue with the current Plan and report in the next Highlight Report
- C.Increase the project budget to absorb the additional cost
- ✓ D.Raise an Exception Report to the Project Board
Why D: When a forecast indicates that a stage or project tolerance will be exceeded, the Project Manager must escalate via an Exception Report to the Project Board. This is management by exception.
Variation 3. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
medium- A.Continue with the current plan and adjust the budget in the next stage
- B.Close the project immediately
- ✓ C.Issue an Exception Report to the Project Board
- D.Reduce the scope to stay within budget without informing the Board
Why C: Management by exception dictates that when a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. Continuing without escalation is not allowed.
Variation 4. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
hard- A.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
- ✓ B.Raise an Exception Report to the Project Board and await their direction before proceeding
- C.Close the project immediately as the Business Case is no longer viable
- D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
Why B: When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is the principle of management by exception.
Variation 5. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
medium- A.Close the project immediately
- ✓ B.Raise an Exception Report to the Project Board
- C.Report in the next Highlight Report
- D.Increase the project budget and continue
Why B: When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. Option C is correct.
Variation 6. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
medium- A.Close the project immediately as the Business Case is no longer viable.
- ✓ B.Raise an Exception Report to the Project Board and await their direction before proceeding.
- C.Increase the project budget to absorb the additional cost and continue with the current Stage Plan.
- D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report.
Why B: When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception. The PM cannot increase the budget or continue without escalation.
Variation 7. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
medium- ✓ A.Raise an Exception Report to the Project Board
- B.Increase the project budget and continue
- C.Continue and report in the next Highlight Report
- D.Close the project as the Business Case is no longer viable
Why A: When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.
Variation 8. A project is forecast to exceed its cost tolerance. What should the Project Manager do?
medium- A.Close the project immediately
- B.Increase the project budget and continue
- ✓ C.Raise an Exception Report to the Project Board
- D.Continue and report in the next Highlight Report
Why C: When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.
Last reviewed: Jun 24, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.