Which role is responsible for defining the project's acceptance criteria?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior User

The Senior User is responsible for defining the acceptance criteria as they represent the users who will accept the final product.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why it's wrong here

    The Project Manager facilitates but does not define acceptance criteria.

  • Executive

    Why it's wrong here

    Executive owns the Business Case but doesn't define acceptance criteria.

  • Senior User

    Why this is correct

    The Senior User defines acceptance criteria on behalf of the users.

  • Senior Supplier

    Why it's wrong here

    The Senior Supplier provides resources but doesn't define acceptance criteria.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.