Question 301 of 1,731
PRINCE2 PracticeshardMultiple ChoiceObjective-mapped

Quick Answer

The correct action is to raise an Issue Report and assess the impact of the workaround. This is required because any deviation from the approved product specifications—known as an off-specification—must be formally documented as an issue within PRINCE2’s issue and change control procedure. The team manager’s unauthorized workaround bypasses the formal approval process, so the Project Manager cannot simply accept it; instead, they must capture it as an Issue Report to investigate the potential consequences on the project’s baselines, costs, and schedule. On the PRINCE2 Foundation exam, this scenario tests your understanding of the Checkpoint Report’s role as a progress reporting tool and the strict protocol for handling unauthorized workarounds. A common trap is thinking the Project Manager can approve the workaround retroactively, but the correct response is always to document and assess first. Memory tip: “No fix without a ticket”—any off-specification, even a clever workaround, must first become a formal Issue Report.

PRINCE2F PRINCE2 Practices Practice Question

This PRINCE2F practice question tests your understanding of prince2 practices. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a stage, the Project Manager receives a Checkpoint Report from a Team Manager indicating that the team has implemented a workaround for an off-specification without prior approval. What should the Project Manager do?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Issue Report and assess the impact of the workaround

Any off-specification must be formally documented as an issue. The team should not have implemented a workaround without approval. The Project Manager should raise an Issue Report and investigate the impact.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Raise an Issue Report and assess the impact of the workaround

    Why this is correct

    The Project Manager should document the issue and assess the impact, then decide on the appropriate action.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Accept the workaround as it has already been implemented

    Why it's wrong here

    The workaround should be formally reviewed and approved; bypassing configuration management is not acceptable.

  • Update the Configuration Item Record to reflect the change

    Why it's wrong here

    The configuration item record should only be updated after formal approval.

  • Instruct the Team Manager to reverse the workaround immediately

    Why it's wrong here

    Reversing may not be the best action; first assess the impact and then decide.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PRINCE2F exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Raise an Issue Report and assess the impact of the workaround — Any off-specification must be formally documented as an issue. The team should not have implemented a workaround without approval. The Project Manager should raise an Issue Report and investigate the impact.

What should I do if I get this PRINCE2F question wrong?

Identify which PRINCE2F exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

6 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During a stage, the Project Manager receives a Checkpoint Report from a Team Manager. What is the primary purpose of this report?

hard
  • A.To communicate progress of a Work Package to the Project Manager
  • B.To request changes to the Work Package
  • C.To escalate issues that cannot be resolved at team level
  • D.To inform the Project Board of stage progress

Why A: A Checkpoint Report is a progress report from the Team Manager to the Project Manager, typically covering the frequency defined in the Work Package.

Variation 2. A Project Manager receives a Checkpoint Report from a Team Manager. What should the Project Manager do with this information?

medium
  • A.Use it to update the Stage Plan and prepare the Highlight Report
  • B.File it without action as it is only for information
  • C.Forward it directly to the Project Board
  • D.Send it to Project Assurance for review

Why A: The Project Manager uses Checkpoint Reports to monitor progress and compile the Highlight Report for the Project Board.

Variation 3. Who is responsible for producing a Checkpoint Report?

medium
  • A.Senior User
  • B.Project Manager
  • C.Team Manager
  • D.Project Support

Why C: Team Managers produce Checkpoint Reports to inform the Project Manager of progress within a Work Package.

Variation 4. Who is responsible for producing a Checkpoint Report?

medium
  • A.Project Manager
  • B.Team Manager
  • C.Senior User
  • D.Project Support

Why B: Team Managers produce Checkpoint Reports to inform the Project Manager of progress against work packages.

Variation 5. What is the purpose of a Checkpoint Report?

medium
  • A.To provide the Project Manager with information on team progress
  • B.To provide the Project Board with information on stage progress
  • C.To report an exception to the Project Board
  • D.To document lessons learned

Why A: A Checkpoint Report is prepared by the Team Manager and given to the Project Manager to report progress at regular intervals (e.g., weekly).

Variation 6. What is the purpose of a Checkpoint Report?

medium
  • A.To document lessons learned
  • B.To report progress of a Work Package from the Team Manager to the Project Manager
  • C.To inform the Project Board of stage progress
  • D.To escalate issues to the Project Board

Why B: The Checkpoint Report is a PRINCE2 management product used by the Team Manager to report progress of a Work Package to the Project Manager. Its purpose is to provide regular, detailed progress updates on the work being performed by the team, ensuring the Project Manager can monitor delivery against the Work Package plan. This is distinct from higher-level reports like the End Stage Report or Highlight Report.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.