A project manager is creating the WBS. Which rule ensures that all deliverables and work required for the project are included in the WBS and no work is omitted?
Trap 1: Rolling wave planning
Rolling wave planning is a progressive elaboration technique, not a completeness rule.
Trap 2: Scope verification
Scope verification is the process of formal acceptance of deliverables, not a WBS rule.
Trap 3: Decomposition rule
Decomposition is the process of breaking down deliverables, not the rule for completeness.
- A
Rolling wave planning
Why wrong: Rolling wave planning is a progressive elaboration technique, not a completeness rule.
- B
Scope verification
Why wrong: Scope verification is the process of formal acceptance of deliverables, not a WBS rule.
- C
100% rule
The 100% rule ensures the WBS contains all work required to complete the project.
- D
Decomposition rule
Why wrong: Decomposition is the process of breaking down deliverables, not the rule for completeness.