PK0-005 Practice Question: A project manager is updating the risk register
A project manager is updating the risk register. Which TWO fields are typically included in a risk register?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Trigger
Common risk register fields include risk ID, description, owner, probability, impact, risk score, response strategy, residual risk, and trigger.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Priority
Why it's wrong here
Priority is typically in the issue log; risk register uses risk score.
- ✗
Issue ID
Why it's wrong here
Issue ID belongs in the issue log, not the risk register.
- ✓
Trigger
Why this is correct
Triggers are warning signs that a risk is about to occur, commonly recorded in the risk register.
- ✓
Risk score
Why this is correct
Risk score, calculated from probability and impact, is a standard risk register field.
- ✗
Resolution date
Why it's wrong here
Resolution date is for issues, not risks.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.