PK0-005 Practice Question: A project manager is updating the risk register

A project manager is updating the risk register. Which TWO fields are typically included in a risk register?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Trigger

Common risk register fields include risk ID, description, owner, probability, impact, risk score, response strategy, residual risk, and trigger.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Priority

    Why it's wrong here

    Priority is typically in the issue log; risk register uses risk score.

  • Issue ID

    Why it's wrong here

    Issue ID belongs in the issue log, not the risk register.

  • Trigger

    Why this is correct

    Triggers are warning signs that a risk is about to occur, commonly recorded in the risk register.

  • Risk score

    Why this is correct

    Risk score, calculated from probability and impact, is a standard risk register field.

  • Resolution date

    Why it's wrong here

    Resolution date is for issues, not risks.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.