Question 859 of 1,731
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is the Starting Up a Project process. This is correct because PRINCE2 mandates that lessons are first formally recorded before the project even begins, during the activity called 'Capture Previous Lessons' within the Starting Up a Project process. The project manager reviews lessons from similar past projects and logs them in the Lessons Log, ensuring the project benefits from prior experience from the outset. On the PRINCE2 Foundation exam, this question tests your understanding of the 'Learn from Experience' principle and its practical application in the process model. A common trap is confusing this with the Managing a Stage Boundary process, where lessons are reviewed and updated, not first recorded. To remember, think: lessons are captured before the project starts, not during execution. A useful mnemonic is "SUP starts the log" — Starting Up a Project is where the Lessons Log is first created.

PRINCE2F PRINCE2 Processes Practice Question

This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During which process are lessons for the project first recorded?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Starting Up a Project

In PRINCE2, the first formal recording of lessons occurs during the 'Starting Up a Project' process. This process includes the activity 'Capture Previous Lessons' (from the 'Learn from Experience' principle), where the project manager reviews lessons from similar previous projects and records them in the Lessons Log before the project is even initiated. This ensures that the project starts with the benefit of past experience.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Initiating a Project

    Why it's wrong here

    IP updates the Lessons Log but it is first created in SU.

  • Managing a Stage Boundary

    Why it's wrong here

    SB captures lessons learned during the stage but the log already exists.

  • Starting Up a Project

    Why this is correct

    The Lessons Log is created in SU and populated with relevant lessons from previous projects.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Closing a Project

    Why it's wrong here

    CP produces the Lessons Report but lessons are recorded earlier.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse 'Initiating a Project' (where detailed planning and the PID are created) with the first recording of lessons, but PRINCE2 explicitly requires lessons to be captured before initiation begins, during the 'Starting Up a Project' process.

Detailed technical explanation

How to think about this question

The Lessons Log is created as a key management product during the 'Starting Up a Project' process. The project manager populates it with lessons from previous projects (e.g., from a corporate lessons database) to inform the Project Brief and Project Plan. This proactive capture is a core part of the 'Learn from Experience' principle, ensuring that the project does not repeat past mistakes from the outset.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Starting Up a Project — In PRINCE2, the first formal recording of lessons occurs during the 'Starting Up a Project' process. This process includes the activity 'Capture Previous Lessons' (from the 'Learn from Experience' principle), where the project manager reviews lessons from similar previous projects and records them in the Lessons Log before the project is even initiated. This ensures that the project starts with the benefit of past experience.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.