Question 757 of 1,731
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is the Team Plan. In PRINCE2, the Team Plan is correct because it is the detailed plan produced by the Project Manager—or delegated to the Team Manager—to provide the Team Manager with specifics on the work to be done within a work package, derived directly from the Stage Plan. This plan breaks down the stage-level objectives into actionable activities, resources, and timelines for the team, ensuring alignment with the overall project goals. On the PRINCE2 Foundation exam, this question tests your understanding of the planning hierarchy and the distinction between management products; a common trap is confusing the Team Plan with the Stage Plan or Project Plan. The key is remembering that the Team Plan is the only plan focused solely on the team’s execution level. For a memory tip, think “Team Plan = Team’s To-Do List” from the Stage Plan.

PRINCE2F PRINCE2 Practices Practice Question

This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

In PRINCE2, which plan is produced by the Project Manager to provide the Team Manager with details of the work to be done?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Team Plan

Option C is correct because in PRINCE2, the Team Plan is produced by the Project Manager (or sometimes the Team Manager) to provide the Team Manager with detailed information about the work to be done at the team level. It is derived from the Stage Plan and focuses on the specific activities, resources, and timelines for a team's work package, ensuring alignment with the overall project objectives.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Exception Plan

    Why it's wrong here

    An Exception Plan is created when tolerances are exceeded.

  • Stage Plan

    Why it's wrong here

    The Stage Plan is for the overall stage, not for a specific team.

  • Team Plan

    Why this is correct

    The Team Plan details the work to be done by a team.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Project Plan

    Why it's wrong here

    The Project Plan is the top-level plan for the entire project.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the Team Plan with the Stage Plan, thinking the Stage Plan provides team-level details, but PRINCE2 explicitly separates these plans by audience and purpose, with the Team Plan being the only one specifically designed for the Team Manager's work instructions.

Detailed technical explanation

How to think about this question

The Team Plan is a PRINCE2 management product that breaks down a work package into specific tasks, often using techniques like product-based planning. It is a key output of the 'Managing Product Delivery' process, where the Team Manager uses it to assign work to team members and monitor progress. In practice, the Team Plan ensures that the team's activities are traceable back to the Stage Plan and Project Plan, maintaining consistency across all planning levels.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Team Plan — Option C is correct because in PRINCE2, the Team Plan is produced by the Project Manager (or sometimes the Team Manager) to provide the Team Manager with detailed information about the work to be done at the team level. It is derived from the Stage Plan and focuses on the specific activities, resources, and timelines for a team's work package, ensuring alignment with the overall project objectives.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project's Stage Plan shows the work for the next stage. Which plan details the work for a team to produce one or more products?

hard
  • A.Stage Plan
  • B.Exception Plan
  • C.Project Plan
  • D.Team Plan

Why D: Option B is correct. A Team Plan is created by the Team Manager to detail the work needed to deliver the products assigned in a Work Package. Stage Plans cover an entire stage; the Project Plan covers the whole project; Exception Plans replace a plan when tolerances are exceeded.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.