Question 893 of 1,731
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is the Progress practice. This is correct because Progress is the PRINCE2 practice specifically designed to monitor actual achievements against planned performance, compare them, and assess the impact of any deviations. When a work package runs over time, the project manager uses Progress to evaluate the effect on the overall schedule and determine whether the deviation falls within agreed tolerances or requires escalation to the project board. On the PRINCE2 Foundation exam, this question tests your understanding of how Progress enables stage-by-stage control and decision-making, often appearing as a scenario where a team manager reports a delay. A common trap is confusing Progress with Plans or Risk; remember that Progress is about comparing actuals to baselines and triggering escalation, not about creating the schedule or managing risk events. A useful memory tip is to think of Progress as the “check and compare” practice: you check the work package status, compare it to the plan, and then decide whether to proceed or escalate.

PRINCE2F PRINCE2 Practices Practice Question

This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a project, a team manager reports that a work package is taking longer than expected. The project manager needs to assess the impact on the project schedule. Which practice should be used to evaluate the effect and determine whether to escalate?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Progress

The Progress practice is used to monitor and compare actual achievements against planned performance, and to assess the impact of deviations. When a work package takes longer than expected, the project manager uses Progress to evaluate the effect on the schedule and decide whether to escalate to the project board. This aligns with PRINCE2's principle of managing by stages and using tolerances to control deviations.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk

    Why it's wrong here

    Risk practice deals with uncertainties, not schedule performance.

  • Plans

    Why it's wrong here

    Plans practice defines the schedule but not the control mechanisms.

  • Organizing

    Why it's wrong here

    Organizing practice defines roles, not control processes.

  • Progress

    Why this is correct

    Progress practice covers monitoring, control, and escalations.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PeopleCert often tests the distinction between 'Risk' (managing future uncertainties) and 'Progress' (monitoring actual performance against baselines), leading candidates to incorrectly select Risk when a delay is already occurring.

Detailed technical explanation

How to think about this question

The Progress practice relies on stage-level and work package-level tolerances (e.g., time, cost, scope) to determine if a deviation is within acceptable limits. If the delay exceeds the work package tolerance, the project manager must escalate to the project board via an exception report. This ensures that control is maintained at the correct management level without bypassing delegated authority.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Progress — The Progress practice is used to monitor and compare actual achievements against planned performance, and to assess the impact of deviations. When a work package takes longer than expected, the project manager uses Progress to evaluate the effect on the schedule and decide whether to escalate to the project board. This aligns with PRINCE2's principle of managing by stages and using tolerances to control deviations.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.