- A
Start a new project to realize more benefits
Why wrong: Not relevant.
- B
Update the Business Case with actual benefits and produce the End Project Report
Correct: finalize documentation.
- C
Delete the project files
Why wrong: Files must be archived, not deleted.
- D
Close the project immediately
Why wrong: Closing requires verification and documentation.
Quick Answer
The answer is to update the Business Case with actual benefits and produce the End Project Report. This is correct because the Closing a Project process requires the project manager to formally confirm benefit realization against the planned benefits in the Business Case, updating it with actual figures to maintain continued business justification. Producing the End Project Report then captures these final benefit measurements along with lessons learned, providing a permanent record for organizational learning and formal project closure. On the PRINCE2 Foundation exam, this question tests your understanding that the closing stage is not just about finishing tasks but about validating the business case’s promised outcomes; a common trap is choosing to simply archive documents or hold a celebration event. Remember the memory tip: “Close with the Case”—always update the Business Case with actual benefits before you produce the End Project Report.
PRINCE2F Business Case and Organizing Practice Question
This PRINCE2F practice question tests your understanding of business case and organizing. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the project manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Update the Business Case with actual benefits and produce the End Project Report
In PRINCE2, the closing stage requires the project manager to formally confirm that all planned benefits have been realized. Updating the Business Case with actual benefits and producing the End Project Report is the correct action because it provides a formal record of benefit realization and lessons learned, which is essential for organizational learning and project closure. This aligns with the PRINCE2 principle of 'continued business justification' and the 'Closing a Project' process.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Start a new project to realize more benefits
Why it's wrong here
Not relevant.
- ✓
Update the Business Case with actual benefits and produce the End Project Report
Why this is correct
Correct: finalize documentation.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Delete the project files
Why it's wrong here
Files must be archived, not deleted.
- ✗
Close the project immediately
Why it's wrong here
Closing requires verification and documentation.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may think closing the project immediately (Option D) is efficient, but PRINCE2 mandates a formal closure process that includes updating the Business Case and producing the End Project Report to ensure accountability and learning.
Detailed technical explanation
How to think about this question
The Business Case is a living document that must be updated with actual benefits during the closing stage to provide a final comparison against planned benefits, ensuring the project's continued business justification is validated. The End Project Report is a mandatory management product that summarizes project performance, including benefit realization, and is used by senior management to assess project success and inform future investments. In real-world scenarios, failing to update the Business Case can lead to inaccurate organizational metrics and poor decision-making for future projects.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Business Case and Organizing — study guide chapter
Learn the concepts, then practise the questions
- →
Business Case and Organizing practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
Business Case and Organizing — This question tests Business Case and Organizing — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Update the Business Case with actual benefits and produce the End Project Report — In PRINCE2, the closing stage requires the project manager to formally confirm that all planned benefits have been realized. Updating the Business Case with actual benefits and producing the End Project Report is the correct action because it provides a formal record of benefit realization and lessons learned, which is essential for organizational learning and project closure. This aligns with the PRINCE2 principle of 'continued business justification' and the 'Closing a Project' process.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.