Who is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Project Manager maintains the Business Case day-to-day, but the Executive (SRO) owns it and is ultimately accountable for the business justification.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior User
Why it's wrong here
The Senior User represents the users' interests and is not responsible for maintaining the Business Case.
- ✓
Project Manager
Why this is correct
The Project Manager is responsible for maintaining the Business Case on behalf of the Executive.
- ✗
Executive
Why it's wrong here
The Executive owns the Business Case but does not maintain it; the Project Manager maintains it.
- ✗
Project Assurance
Why it's wrong here
Project Assurance provides independent oversight, not maintenance of the Business Case.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.