Which TWO of the following are key characteristics of a project? (Select TWO.)
Uniqueness is a defining trait of a project.
Why this answer
A project is defined by its temporary nature and unique outcome. Option B is correct because a project creates a unique product, service, or result, distinguishing it from ongoing operations. This uniqueness is a core characteristic per the PMBOK Guide, which defines a project as a temporary endeavor undertaken to create a unique deliverable.
Exam trap
CompTIA often tests the distinction between projects and operations by presenting 'ongoing' or 'routine' work as a project characteristic, tempting candidates who confuse operational stability with project execution.