PK0-005 Practice Question: A project manager is developing the project…

A project manager is developing the project management plan. The sponsor requests detailed cost estimates for each work package, but the activities have not yet been defined. What should the project manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Defer the cost estimates until after activity definition.

Detailed cost estimates require that activities are defined first, as per the typical planning process sequence (e.g., PMBOK). Without activity definition, the project manager cannot accurately estimate costs for each work package. Option A is wrong because analogous estimating provides rough estimates, not detailed ones, and is used when little information is available—not suitable for this scenario. Option B is wrong because a rough order of magnitude estimate is not detailed and does not meet the sponsor's request for detailed cost estimates. Option D is wrong because breaking down work packages into activities is part of activity definition, which has not yet been done; bottom-up estimates should follow activity definition, not precede it.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Use analogous estimating to provide rough estimates.

    Why it's wrong here

    Analogous estimating gives rough estimates, not the detailed estimates requested by the sponsor.

  • Ask the sponsor to approve a rough order of magnitude estimate.

    Why it's wrong here

    A rough order of magnitude estimate is not detailed, and the sponsor requested detailed estimates.

  • Defer the cost estimates until after activity definition.

    Why this is correct

    Activity definition must precede detailed cost estimation to ensure accuracy.

  • Break down the work packages into activities and create bottom-up estimates.

    Why it's wrong here

    This is premature because activity definition has not yet been done; bottom-up estimates require defined activities.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.