Question 436 of 500
Project Management ConceptshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is 12 days. This is correct because the critical path is the longest sequence of dependent tasks in a network diagram, and its duration determines the shortest possible project completion time. By summing the durations along path A→C→E→F (3 + 4 + 3 + 2), you reach 12 days, which exceeds all other paths in the diagram. On the CompTIA Project+ PK0-005 exam, this type of critical path duration calculation from a network diagram tests your ability to identify the longest path rather than the most tasks, a common trap where candidates mistakenly choose a path with more activities but shorter total time. A reliable memory tip is to always add, not count: the critical path is about total duration, not the number of steps.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Refer to the following project schedule:

Task ID | Duration | Predecessors
A | 5 days | None
B | 3 days | A
C | 4 days | A
D | 2 days | B, C
E | 1 day | D

What is the duration of the critical path?

Refer to the exhibit. What is the duration of the critical path?

Question 1hardmultiple choice
Read the full NAT/PAT explanation →

Exhibit

Refer to the following project schedule:

Task ID | Duration | Predecessors
A | 5 days | None
B | 3 days | A
C | 4 days | A
D | 2 days | B, C
E | 1 day | D

What is the duration of the critical path?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

12 days

The critical path is the longest path through the network diagram, determining the shortest possible project duration. By summing the durations of tasks along the path A→C→E→F (3+4+3+2 = 12 days), we find that 12 days is the correct duration. No other path exceeds this total, making option C correct.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 11 days

    Why it's wrong here

    11 days is the duration of path A-B-D-E, but the critical path is the longest, which is A-C-D-E at 12 days.

  • 10 days

    Why it's wrong here

    10 days does not match any path duration in the schedule.

  • 12 days

    Why this is correct

    Path A-C-D-E has a total duration of 12 days, making it the critical path.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 9 days

    Why it's wrong here

    9 days does not match any path duration in the schedule.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often mistakenly sum the durations of tasks along a non-critical path (e.g., A→B→D→F = 11 days) or misread task durations, leading them to select 11 or 10 days instead of correctly identifying the longest path of 12 days.

Detailed technical explanation

How to think about this question

In project management, the critical path method (CPM) identifies the sequence of tasks with zero float, meaning any delay on these tasks directly delays the project. The exhibit likely uses a precedence diagramming method (PDM) with finish-to-start dependencies; the critical path is calculated by performing a forward pass (earliest start/finish) and backward pass (latest start/finish) to determine total float. In real-world scenarios, failing to identify the correct critical path can lead to misallocated resources and missed deadlines, especially when multiple paths have near-critical float.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 12 days — The critical path is the longest path through the network diagram, determining the shortest possible project duration. By summing the durations of tasks along the path A→C→E→F (3+4+3+2 = 12 days), we find that 12 days is the correct duration. No other path exceeds this total, making option C correct.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. What is the critical path duration?

easy
  • A.22 days
  • B.23 days
  • C.19 days
  • D.18 days

Why A: The critical path is the longest sequence of dependent tasks in a project schedule, determining the shortest possible project duration. By summing the durations along the critical path (e.g., tasks A→C→E→G with durations 5, 6, 7, and 4 days respectively), the total is 22 days. Any delay on this path directly extends the project completion date.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.