- A
Crash the schedule by adding overtime.
Overtime can accelerate critical path.
- B
Fast track remaining tasks.
Why wrong: Increases risk and may cause rework.
- C
Implement resource smoothing.
Why wrong: Smoothing doesn't shorten critical path.
- D
Resource level to balance workload.
Why wrong: Leveling often extends schedule.
Quick Answer
The answer is to crash the schedule by adding overtime. This technique minimizes schedule impact because it directly increases the work hours available for critical path tasks without requiring additional personnel, which is essential when no backup resources exist and the deadline is tight. On the CompTIA Project+ PK0-005 exam, this scenario tests your understanding of schedule compression techniques, specifically the distinction between crashing (adding resources or overtime to critical path tasks) and fast-tracking (performing tasks in parallel). A common trap is choosing fast-tracking, but that increases risk and does not address the loss of a team member’s capacity. Remember that crashing with overtime leverages the existing team’s extra effort to recover lost time, making it the only viable option here. Memory tip: “Crash with cash or clock” — crashing either adds more people (cash) or more hours (clock/overtime).
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During project execution, a critical team member resigns. The project manager must reassign tasks. The project has a tight deadline and no backup resources. Which technique best minimizes schedule impact?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"best"Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Crash the schedule by adding overtime.
Crashing the schedule by adding overtime directly increases the work hours available to complete critical path tasks without requiring additional resources. Since the project has no backup resources and a tight deadline, overtime is the only option that can compress the schedule by applying more effort to the existing team, thereby minimizing the schedule impact from the resignation.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Crash the schedule by adding overtime.
Why this is correct
Overtime can accelerate critical path.
Clue confirmation
The clue word "best" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Fast track remaining tasks.
Why it's wrong here
Increases risk and may cause rework.
- ✗
Implement resource smoothing.
Why it's wrong here
Smoothing doesn't shorten critical path.
- ✗
Resource level to balance workload.
Why it's wrong here
Leveling often extends schedule.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the distinction between schedule compression techniques (crashing vs. fast-tracking) and resource optimization techniques (smoothing vs. leveling), and the trap here is that candidates confuse resource smoothing or leveling with schedule compression, not realizing they adjust resource usage without necessarily reducing project duration.
Detailed technical explanation
How to think about this question
Crashing is a schedule compression technique that focuses on the critical path by adding resources or overtime to critical activities, with the trade-off of increased cost. In this scenario, overtime effectively increases the team's available hours per day (e.g., from 8 to 10 or 12 hours), allowing the remaining members to absorb the departed member's tasks without hiring or cross-training new resources. Real-world project management software like Microsoft Project calculates crash cost per unit time to determine the most cost-effective way to reduce duration, but here the constraint is no backup resources, making overtime the only viable crash method.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Crash the schedule by adding overtime. — Crashing the schedule by adding overtime directly increases the work hours available to complete critical path tasks without requiring additional resources. Since the project has no backup resources and a tight deadline, overtime is the only option that can compress the schedule by applying more effort to the existing team, thereby minimizing the schedule impact from the resignation.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.