Question 270 of 1,731
Overview of PRINCE2 and the project environmentmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is the Senior Responsible Owner (Executive), who is ultimately accountable for maintaining the business case in PRINCE2. This role owns the business case from the start of the project through to its closure, ensuring the project remains viable and aligned with organizational objectives. While the Project Manager handles the day-to-day maintenance and updates of the business case document, accountability rests solely with the Senior Responsible Owner, who must approve any changes to the justification. On the PRINCE2 Foundation exam, this distinction is a frequent trap: candidates often confuse the Project Manager’s operational maintenance with the Executive’s ultimate responsibility. A common memory tip is to remember that the Executive “owns the why”—the business case justifies the project, and only the person who signs off on it can be accountable for keeping it valid. Think of it as the Executive holding the financial and strategic keys, while the Project Manager merely turns the lock each day.

PRINCE2F Practice Question: Overview of PRINCE2 and the project environment

This PRINCE2F practice question tests your understanding of overview of prince2 and the project environment. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which role is responsible for maintaining the Business Case throughout the project?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior Responsible Owner (Executive)

The Senior Responsible Owner (Executive) is accountable for the Business Case. Option B is correct. The Project Manager maintains the Business Case on a day-to-day basis but is not ultimately responsible. The Team Manager does not have this responsibility. The Change Authority is responsible for change decisions, not the Business Case.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Team Manager

    Why it's wrong here

    Team Managers are responsible for delivering work packages.

  • Senior Responsible Owner (Executive)

    Why this is correct

    The Executive is responsible for the Business Case.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Change Authority

    Why it's wrong here

    The Change Authority is responsible for change control decisions.

  • Project Manager

    Why it's wrong here

    The Project Manager maintains the Business Case on a day-to-day basis but the Executive is accountable.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PRINCE2F exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

Overview of PRINCE2 and the project environment — This question tests Overview of PRINCE2 and the project environment — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Senior Responsible Owner (Executive) — The Senior Responsible Owner (Executive) is accountable for the Business Case. Option B is correct. The Project Manager maintains the Business Case on a day-to-day basis but is not ultimately responsible. The Team Manager does not have this responsibility. The Change Authority is responsible for change decisions, not the Business Case.

What should I do if I get this PRINCE2F question wrong?

Identify which PRINCE2F exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

8 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which role is responsible for maintaining the Business Case throughout the project?

medium
  • A.Senior Supplier
  • B.Senior User
  • C.Executive
  • D.Project Manager

Why C: The Executive (Senior Responsible Owner) owns the Business Case and is responsible for its maintenance.

Variation 2. Who is responsible for maintaining the Business Case throughout the project?

easy
  • A.The Project Manager
  • B.The Senior Supplier
  • C.The Executive
  • D.The Senior User

Why C: Option A is correct. The Executive (Senior Responsible Owner) is responsible for the Business Case. The Project Manager maintains it on a day-to-day basis but the Executive owns it.

Variation 3. Who is responsible for maintaining the Business Case throughout the project?

medium
  • A.Project Manager
  • B.Senior User
  • C.Executive
  • D.Senior Supplier

Why C: The Executive (Senior Responsible Owner) owns the Business Case and is responsible for its maintenance.

Variation 4. Who is responsible for maintaining the Business Case throughout the project?

easy
  • A.Project Assurance
  • B.Senior User
  • C.Project Manager
  • D.Executive (Senior Responsible Owner)

Variation 5. Who is responsible for maintaining the Business Case throughout the project?

medium
  • A.Project Manager
  • B.Senior User
  • C.Executive
  • D.Senior Supplier

Why C: The Executive (Senior Responsible Owner) is the owner of the Business Case and is accountable for its development and maintenance. The Project Manager may assist in its creation but does not own it.

Variation 6. Who is responsible for maintaining the Business Case throughout the project?

easy
  • A.Project Assurance
  • B.Senior User
  • C.Executive
  • D.Project Manager

Why C: The Executive is responsible for the Business Case. Option A is correct. The Project Manager develops and maintains the PID but not the Business Case. The Senior User ensures benefits are realized. The Project Assurance role is independent.

Variation 7. Who is responsible for maintaining the Business Case throughout the project?

medium
  • A.The Executive
  • B.The Project Manager
  • C.The Project Support
  • D.The Senior User

Why B: The Senior User is responsible for specifying the benefits and ensuring they are realized, but the Executive owns the Business Case. The Project Manager maintains it on a day-to-day basis.

Variation 8. Who is responsible for maintaining the Business Case throughout the project?

medium
  • A.Project Manager
  • B.Senior User
  • C.Executive
  • D.Project Support

Why C: The Senior User represents the users and is responsible for ensuring the project delivers the required benefits; however, the Executive (Senior Responsible Owner) owns the Business Case. In PRINCE2, the Executive is ultimately accountable for the Business Case, but the Senior User provides input on benefits. The question asks who maintains it, and the correct answer is the Executive.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.