CCNA Prince2 People Questions

35 of 335 questions · Page 5/5 · Prince2 People topic · Answers revealed

301
MCQhard

What is the key difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An RFC is raised by the Project Board; an Off-spec is raised by the Project Manager
B.There is no difference; they are two names for the same thing
C.An RFC suggests a change to what is specified; an Off-spec reports that something does not meet its specification
D.An RFC is always urgent; an Off-spec is not
AnswerC

This captures the fundamental difference.

Why this answer

An RFC proposes a modification to an agreed baseline, while an Off-spec is a product not meeting its specification (a deviation).

302
MCQhard

In PRINCE2, what is the difference between a risk owner and a risk actionee?

A.The risk owner is a member of the Project Board; the risk actionee is a team member
B.The risk owner is accountable for the risk; the risk actionee performs the risk response actions
C.The risk owner identifies the risk; the risk actionee implements the response
D.They are the same role
AnswerB

Correct.

Why this answer

The risk owner is responsible for managing the risk overall, while the risk actionee is assigned to carry out specific actions to respond to the risk.

303
Multi-Selecthard

Which THREE of the following are purposes of the Directing a Project process?

Select 3 answers
A.Ensure the project remains viable
B.Confirm the project closure
C.Manage the day-to-day activities of the project
D.Authorize a stage plan
E.Authorize the initiation of the project
AnswersB, D, E

The Board confirms closure.

Why this answer

Option B is correct because one of the key purposes of the Directing a Project process is to confirm project closure, ensuring that all objectives have been met and that the project is formally closed. This includes authorizing the final stage and confirming that the project has delivered its products as defined in the Project Initiation Documentation.

Exam trap

PeopleCert often tests the distinction between the project board's strategic oversight (Directing a Project) and the project manager's tactical control (Managing a Stage Boundary), causing candidates to confuse viability checks with day-to-day management.

304
MCQmedium

During the Controlling a Stage process, a Work Package is authorized by the Project Manager. Who is responsible for delivering the Work Package?

A.Senior Supplier
B.Project Support
C.Team Manager
D.Project Manager
AnswerC

Correct: The Team Manager manages the work and delivers the Work Package.

Why this answer

In PRINCE2, the Team Manager is the role responsible for delivering the Work Package authorized by the Project Manager during the Controlling a Stage process. The Team Manager coordinates the team's work, ensures the products meet the agreed quality criteria, and reports progress back to the Project Manager.

Exam trap

The trap here is that candidates often confuse the Project Manager's role of authorizing the Work Package with the responsibility for its delivery, leading them to select the Project Manager instead of the Team Manager.

How to eliminate wrong answers

Option A is wrong because the Senior Supplier is responsible for providing supplier resources and expertise, not for directly delivering the Work Package. Option B is wrong because Project Support provides administrative and advisory services, such as configuration management and reporting, but does not deliver the Work Package. Option D is wrong because the Project Manager authorizes the Work Package and manages the stage, but the actual delivery is delegated to the Team Manager.

305
MCQmedium

A project manager notices that team members are frequently bypassing the project's defined escalation paths and going directly to senior stakeholders with issues. This is causing confusion and undermining the project's governance. Which PRINCE2 principle is being violated?

A.Defined roles and responsibilities
B.Learn from experience
C.Manage by stages
D.Continued business justification
AnswerC

This principle involves planning, monitoring, and controlling by stages, which includes defined escalation paths.

Why this answer

The correct answer is C, 'Manage by stages,' because the PRINCE2 principle of managing by stages requires that each stage be planned, monitored, and controlled with defined escalation paths for issues. When team members bypass these paths and go directly to senior stakeholders, they undermine the stage-by-stage control and governance, violating the principle that decisions and escalations should follow the established stage boundaries and management levels.

Exam trap

PeopleCert often tests the distinction between 'roles and responsibilities' (who does what) and 'manage by stages' (how control is exercised over time); the trap here is that candidates see a governance breakdown and incorrectly attribute it to unclear roles rather than the violation of stage-based escalation control.

How to eliminate wrong answers

Option A is wrong because 'Defined roles and responsibilities' focuses on clarity of who does what, not on the escalation or stage-based control; bypassing escalation paths is a governance issue, not a role definition issue. Option B is wrong because 'Learn from experience' is about capturing and applying lessons, not about enforcing escalation procedures or stage governance. Option D is wrong because 'Continued business justification' concerns ongoing viability of the project, not the operational control of how issues are escalated within stages.

306
MCQhard

Which of the following statements best describes the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

A.An RFC is handled by the Change Authority, while an Off-spec is handled by the Project Manager
B.An RFC always results in a change to the Baseline, while an Off-spec always results in a concession
C.An RFC proposes a change to an approved product or process, while an Off-spec identifies a product that does not meet its specification
D.An RFC is raised by the Senior User, while an Off-spec is raised by the Project Manager
AnswerC

This is the accurate distinction: RFC is a change request; Off-spec is a product non-conformance.

Why this answer

Option C is correct because a Request for Change (RFC) is a formal proposal to modify a product, baseline, or process that has been approved, while an Off-Specification (Off-spec) is a formal notification that a product does not meet its agreed specification. In PRINCE2, an RFC seeks to change what is required, whereas an Off-spec reports a failure to deliver what was required. This distinction is fundamental to the issue and change control procedure.

Exam trap

PeopleCert often tests the misconception that RFCs and Off-specs are handled by different roles or always lead to specific outcomes, when in reality both can be raised by anyone and their resolution depends on the change authority and the nature of the issue.

How to eliminate wrong answers

Option A is wrong because both RFCs and Off-specs can be handled by the Change Authority or the Project Manager depending on the delegation of authority and the severity of the issue; there is no fixed rule that RFCs go to the Change Authority and Off-specs go to the Project Manager. Option B is wrong because an RFC does not always result in a change to the baseline (it may be rejected), and an Off-spec does not always result in a concession (it may be resolved by a corrective action or a change request). Option D is wrong because an RFC can be raised by any stakeholder (not just the Senior User), and an Off-spec is typically raised by the person who identifies the non-conformance, which could be the Project Manager, team manager, or quality assurance, not exclusively the Project Manager.

307
MCQeasy

In PRINCE2, what is the purpose of Project Support?

A.To provide administrative support to the project.
B.To approve stage plans.
C.To independently assure the Project Board.
D.To manage the project's budget.
AnswerA

Project Support is an optional administrative role.

Why this answer

Project Support in PRINCE2 is a role that provides administrative and clerical services to the project management team, such as maintaining files, organizing meetings, and managing project documentation. It does not have decision-making authority over stage plans, assurance, or budget management, which are the responsibilities of other roles like the Project Manager, Project Assurance, and the Executive.

Exam trap

The trap here is that candidates confuse Project Support with Project Assurance, mistakenly thinking support includes oversight or approval functions, when in fact PRINCE2 strictly separates administrative support from independent assurance and management authority.

How to eliminate wrong answers

Option B is wrong because approving stage plans is the responsibility of the Project Board, not Project Support. Option C is wrong because independent assurance of the Project Board is the role of Project Assurance, which is separate from Project Support. Option D is wrong because managing the project's budget is a core duty of the Project Manager, not Project Support.

308
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Initiation Documentation
B.Business Case
C.Stage Plan
D.Project Brief
AnswerA

The PID is the comprehensive document produced during initiation.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project. It brings together all the information needed to start the project and is used by the Project Board to decide whether to proceed.

309
MCQmedium

In PRINCE2, what is the role of the Senior User?

A.To specify the desired outcomes and benefits
B.To chair the Project Board
C.To manage the project on a day-to-day basis
D.To provide resources and expertise
AnswerA

Correct: The Senior User defines what is needed and ensures benefits are realized.

Why this answer

The Senior User represents those who will use the project's products, specifies the benefits, and ensures the project delivers them. They are also accountable for the Business Case's benefits realization.

310
Multi-Selecthard

Which THREE of the following are true regarding Project Assurance?

Select 3 answers
A.It includes business, user, and supplier perspectives
B.It is performed exclusively by the Executive
C.It cannot be delegated to the Project Manager
D.It is optional in PRINCE2
E.It is independent of the Project Manager
AnswersA, C, E

Correct.

Why this answer

Project Assurance is a PRINCE2 role that provides independent oversight of the project's ongoing viability, compliance, and quality from three distinct perspectives: business, user, and supplier. Option A is correct because the PRINCE2 framework explicitly requires Project Assurance to cover all three stakeholder viewpoints to ensure balanced governance and that the project remains aligned with business objectives, user needs, and supplier capabilities.

Exam trap

The trap here is that candidates often confuse the Executive's responsibility for ensuring Project Assurance with the mistaken belief that the Executive must personally perform all assurance activities, leading them to incorrectly select Option B.

311
MCQmedium

Which role is responsible for producing the Highlight Report?

A.Project Support
B.Project Manager
C.Senior Responsible Owner
D.Team Manager
AnswerB

The PM produces the Highlight Report.

Why this answer

The Highlight Report is a progress report that summarizes the status of a management stage for the Project Board. According to PRINCE2, the Project Manager is responsible for producing the Highlight Report at intervals defined in the Communication Management Strategy, typically to keep the Project Board informed of progress, exceptions, and forecasts.

Exam trap

The trap here is that candidates often confuse the Highlight Report with the Checkpoint Report, mistakenly assigning the Team Manager as the producer, when in fact the Team Manager produces the Checkpoint Report and the Project Manager produces the Highlight Report.

How to eliminate wrong answers

Option A is wrong because Project Support provides administrative and clerical assistance, such as maintaining files or distributing reports, but does not own the production of the Highlight Report. Option C is wrong because the Senior Responsible Owner (SRO) is the executive accountable for the business case and overall project success, not for producing operational progress reports like the Highlight Report. Option D is wrong because the Team Manager is responsible for producing the Checkpoint Report for their team, not the stage-level Highlight Report, which is a higher-level summary compiled by the Project Manager.

312
MCQhard

A project is in the Managing a Stage Boundary process. The Project Manager discovers that the stage is likely to overrun its time tolerance. The Project Board has not yet approved the next Stage Plan. What should the Project Manager do?

A.Raise an Exception Report to the Project Board.
B.Update the Project Plan to reflect the delay.
C.Close the project as the Business Case is invalid.
D.Continue with the current Stage Plan and submit the next Stage Plan as planned.
AnswerA

The PM must escalate via an Exception Report.

Why this answer

When a stage is forecast to exceed tolerance, the Project Manager must produce an Exception Report and submit it to the Project Board for decision. This is part of management by exception.

313
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Board?

Select 3 answers
A.Defining project tolerances
B.Preparing the Highlight Report
C.Authorizing the start of each management stage
D.Approving the Project Plan
E.Managing the team's day-to-day activities
AnswersA, C, D

The Project Board sets tolerances for the project.

Why this answer

The Project Board is responsible for strategic decisions: approving plans, defining tolerances, and authorizing stage boundaries. Day-to-day management is the PM's role.

314
Multi-Selectmedium

Which TWO of the following are optional roles in the PRINCE2 project management team?

Select 2 answers
A.Project Board
B.Project Support
C.Senior Supplier
D.Project Manager
E.Change Authority
AnswersB, E

Optional role for administrative support.

Why this answer

Option B is correct because Project Support is an optional role in PRINCE2, providing administrative and advisory services to the project manager and team, but it is not mandatory for the project management team structure. Option E is correct because the Change Authority role is also optional, delegated by the Project Board to manage change requests and off-specifications, and is only established if needed for change control.

Exam trap

PeopleCert often tests the misconception that all roles listed in the PRINCE2 management team are mandatory, leading candidates to incorrectly select roles like Project Support or Change Authority as required, when they are actually optional and only established when needed.

315
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Increase the stage budget and continue with the current plan
B.Continue with the plan and report the overrun in the next Highlight Report
C.Raise an Exception Report to the Project Board and await direction
D.Close the project immediately as the Business Case is no longer viable
AnswerC

This follows management by exception: the PM escalates when tolerances are forecast to be breached.

Why this answer

Option C is correct because PRINCE2 dictates that when a project manager forecasts a deviation beyond the stage's cost tolerance, they must raise an Exception Report to the Project Board. The Project Board then decides on corrective action, such as approving a revised plan or closing the project. This ensures governance and control over the project's financial limits.

Exam trap

The trap here is that candidates confuse the Highlight Report (used for routine progress within tolerance) with the Exception Report (mandatory for forecast tolerance breaches), leading them to incorrectly select Option B.

How to eliminate wrong answers

Option A is wrong because the Project Manager cannot unilaterally increase the stage budget; only the Project Board can authorize a budget change via an exception plan. Option B is wrong because the Highlight Report is for reporting progress within tolerance, not for escalating a forecasted tolerance breach; the Exception Report is the mandatory mechanism for such deviations. Option D is wrong because the Business Case may still be viable; the Project Board must assess the situation and decide whether to continue, not the Project Manager acting alone.

316
MCQmedium

Who chairs the Project Board meetings in PRINCE2?

A.Senior Supplier
B.Project Manager
C.Senior User
D.Senior Responsible Owner (Executive)
AnswerD

The SRO chairs the Project Board.

Why this answer

The Executive (Senior Responsible Owner) chairs the Project Board meetings in PRINCE2 because they are ultimately accountable for the project's success and have the authority to make key decisions. This role ensures the project remains aligned with business objectives and provides strategic direction during board meetings.

Exam trap

The trap here is that candidates often confuse the Project Manager's role in facilitating meetings with the authority to chair the board, but PRINCE2 clearly separates management (Project Manager) from governance (Executive chairing the board).

How to eliminate wrong answers

Option A is wrong because the Senior Supplier represents the interests of those providing the project's products and does not chair the board; they focus on technical feasibility and supplier-side concerns. Option B is wrong because the Project Manager is responsible for day-to-day management and reporting to the board, not chairing it, as they lack the authority to make strategic decisions. Option C is wrong because the Senior User represents the needs of those who will use the project's outputs and does not chair the board; their role is to define requirements and ensure benefits realization.

317
MCQeasy

Which role is responsible for managing the day-to-day activities of the project within the tolerances set by the Project Board?

A.Project Manager
B.Project Assurance
C.Team Manager
D.Senior Responsible Owner (SRO)
AnswerA

The Project Manager has authority to manage the project within tolerances.

Why this answer

The Project Manager is responsible for day-to-day management of the project within tolerances set by the Project Board.

318
Multi-Selectmedium

Which THREE of the following are elements of the PRINCE2 project management team?

Select 3 answers
A.Project Board
B.Team Manager
C.Project Manager
D.User Group
E.Steering Committee
AnswersA, B, C

Correct: The Project Board is the top-level decision-making body.

Why this answer

The PRINCE2 project management team includes the Project Board (Executive, Senior User, Senior Supplier), Project Manager, Team Manager, and optionally Project Assurance and Project Support. User group and Steering Committee are not PRINCE2 terms.

319
MCQhard

Why does PRINCE2 separate the role of Project Manager from Project Assurance?

A.To allow the Project Manager to focus on day-to-day management while assurance is independent
B.To reduce the workload of the Project Manager
C.To avoid the need for quality reviews
D.To ensure that the Project Board has direct control over the team
AnswerA

Correct: Independence ensures objective oversight and avoids conflict of interest.

Why this answer

PRINCE2 separates the role of Project Manager from Project Assurance to ensure that assurance activities are performed independently of day-to-day management. This allows the Project Manager to focus on delivering the project's products and managing the team, while Project Assurance provides an objective check that the project remains viable, compliant with standards, and aligned with business expectations. The independence prevents conflicts of interest and ensures that assurance is not compromised by the pressures of daily project work.

Exam trap

The trap here is that candidates often confuse the separation of roles with workload reduction, but PRINCE2 explicitly mandates independence of assurance to maintain objectivity, not to lighten the Project Manager's load.

How to eliminate wrong answers

Option B is wrong because reducing the Project Manager's workload is a potential side effect, not the primary reason for the separation; the core principle is independence of assurance, not workload distribution. Option C is wrong because quality reviews are a separate PRINCE2 technique that still occur regardless of the separation; the separation does not eliminate the need for quality reviews. Option D is wrong because the Project Board does not gain direct control over the team through this separation; the Project Board retains strategic control via management stages and tolerances, while the Project Manager handles day-to-day team management.

320
MCQhard

What is the difference between Project Assurance and a quality review?

A.Project Assurance is a role providing ongoing independent oversight; a quality review is a technique to evaluate product quality
B.Project Assurance is performed by the Project Manager; quality review is performed by the team
C.There is no difference; quality review is another name for Project Assurance
D.Project Assurance focuses on benefits; quality review focuses on products
AnswerA

This captures the essential difference.

Why this answer

Project Assurance is a continuous, independent oversight role for the Project Board, while a quality review is a specific technique to assess product quality at a point in time.

321
MCQmedium

The Project Board has not met for several months. According to PRINCE2, when should the Project Board meet?

A.Weekly
B.Monthly
C.At stage boundaries and when an Exception Report is raised
D.Only at the end of the project
AnswerC

Project Board meetings are typically held at stage boundaries and when escalation is needed via Exception Reports.

Why this answer

PRINCE2 recommends that Project Boards meet at the end of each management stage (Stage Boundary) and when an Exception Report is raised. They should not meet on a fixed monthly basis; meetings are exception-driven.

322
MCQhard

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue and report the overrun in the next Highlight Report
B.Increase the budget and continue with the current plan
C.Close the project as the Business Case is no longer viable
D.Raise an Exception Report to the Project Board
AnswerD

The Exception Report is the formal mechanism to escalate tolerance deviations to the Project Board.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is the principle of management by exception.

323
Multi-Selecthard

Which TWO statements about the Project Board's responsibilities in PRINCE2 are correct?

Select 2 answers
A.It is responsible for the day-to-day management of the project.
B.It provides direction and control to the Project Manager.
C.It meets on an exception-driven basis.
D.It is responsible for preparing the Stage Plans.
E.It is accountable for the overall success of the project.
AnswersC, E

The Project Board meets only when necessary, typically via exception reports.

Why this answer

The Project Board is responsible for providing overall direction and control to the Project Manager, but it does not handle day-to-day management. It meets on an exception-driven basis to review and decide on exception reports when a project deviates significantly from its tolerances, ensuring management by exception is applied. This is a core PRINCE2 principle that allows the board to focus on strategic decisions rather than routine operations.

Exam trap

PeopleCert often tests the distinction between 'accountability' and 'responsibility' — the trap here is confusing the Project Board's accountability for overall success (Option E) with the Project Manager's responsibility for day-to-day management (Option A), leading candidates to incorrectly select A or D.

324
Multi-Selecthard

Which THREE of the following are true about the role of the Change Authority?

Select 3 answers
A.It has the authority to approve change requests within limits set by the Project Board
B.It is responsible for raising all Requests for Change
C.It is responsible for maintaining the Configuration Item Records
D.It is an optional role in PRINCE2
E.It can be a person or a group
AnswersA, D, E

The Board delegates authority to the Change Authority for certain decisions.

Why this answer

The Change Authority is an optional role delegated by the Project Board to make decisions on change requests within defined limits. They can approve RFCs up to a certain cost or impact. They are not responsible for configuration management or raising RFCs.

325
MCQhard

In PRINCE2, what is the recommended leadership style for a Project Manager when dealing with a team that has high competence and low commitment?

A.Supporting
B.Coaching
C.Delegating
D.Directing
AnswerA

Supporting is appropriate for high competence and low commitment to boost morale and engagement.

Why this answer

In PRINCE2, the recommended leadership style for a Project Manager when the team has high competence but low commitment is Supporting (S3). This is because the team already possesses the necessary skills and knowledge (high competence) but lacks motivation or confidence (low commitment), so the PM should focus on encouraging, praising, and involving them in decision-making rather than providing technical direction or close supervision.

Exam trap

The trap here is that candidates often confuse 'Supporting' with 'Coaching' because both involve supportive behaviors, but coaching is specifically for building competence, not for addressing low commitment in an already competent team.

How to eliminate wrong answers

Option B (Coaching) is wrong because coaching is appropriate when the team has low competence but high commitment, requiring the PM to provide both direction and support to build skills. Option C (Delegating) is wrong because delegating is used when the team has both high competence and high commitment, allowing the PM to hand over responsibility with minimal oversight. Option D (Directing) is wrong because directing is for teams with low competence and low commitment, where the PM must give clear instructions and close supervision.

326
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Support role?

Select 3 answers
A.Providing independent assurance to the Project Board
B.Preparing the Highlight Report
C.Assisting with planning and scheduling
D.Providing administrative support to the project team
E.Maintaining the project filing system
AnswersC, D, E

Planning support is a common function of Project Support.

Why this answer

Project Support provides administrative and support services, such as maintaining files, providing planning support, and managing project administration.

327
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification?

A.An RFC is raised by the Project Manager; an Off-specification is raised by the team.
B.An RFC is related to cost; an Off-specification is related to time.
C.An RFC seeks to change a product's specification; an Off-specification occurs when a product does not meet its specification.
D.There is no difference; they are the same.
AnswerC

Correct. RFC proposes a change; Off-spec is a deviation from the existing specification.

Why this answer

An RFC proposes a change or enhancement; an Off-specification is a product that fails to meet its specification. Both are issues but differ in cause.

328
MCQmedium

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An RFC requires an Exception Plan; an Off-spec requires a corrective action
B.An RFC proposes a change; an Off-spec identifies a failure to meet a requirement
C.An RFC is always approved by the Change Authority; an Off-spec is always approved by the Project Board
D.An RFC is raised by the Project Board; an Off-spec is raised by the Project Manager
AnswerB

An RFC is a request for a desired change; an Off-spec is when a product does not meet its specification.

Why this answer

An RFC is a proposal for a change that adds value or modifies requirements; an Off-spec is something that should be provided but is not (e.g., a defect or omission).

329
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change proposes a change to an agreed product; an Off-specification identifies a product that is not meeting its specification.
B.A Request for Change is about cost; an Off-specification is about quality.
C.A Request for Change is raised by the Project Manager; an Off-specification is raised by the Team Manager.
D.They are the same thing.
AnswerA

This is the correct distinction.

Why this answer

Option A is correct because a Request for Change (RFC) is a formal proposal to modify an agreed product, baseline, or configuration item, while an Off-specification (Off-spec) is a notification that a product does not meet its agreed specification. In PRINCE2, these are distinct issue types: RFCs seek authorization for a change, whereas Off-specs report a deviation from the specification that must be resolved.

Exam trap

The trap here is that candidates often conflate the two concepts because both involve deviations from the plan, but PRINCE2 explicitly separates them by intent: RFCs are proactive changes, while Off-specs are reactive reports of non-compliance.

How to eliminate wrong answers

Option B is wrong because both RFCs and Off-specs can have cost and quality implications; RFCs are not exclusively about cost, nor are Off-specs exclusively about quality. Option C is wrong because both RFCs and Off-specs can be raised by any project role, not limited to Project Manager or Team Manager; the PRINCE2 guidance does not restrict who raises them. Option D is wrong because RFCs and Off-specs are fundamentally different: one proposes a change, the other reports a failure to meet specification.

330
MCQmedium

Which PRINCE2 role is responsible for ensuring that the project's products meet the required quality criteria?

A.Project Manager
B.Senior User
C.Project Assurance
D.Senior Supplier
AnswerB

The Senior User defines the desired outcomes and ensures that the products meet quality expectations.

Why this answer

The Senior User is responsible for specifying the required quality criteria for the project's products and ensuring that the delivered products meet those criteria. This role represents the interests of those who will use the project's outputs and is accountable for defining acceptance standards and verifying that products satisfy the defined quality expectations.

Exam trap

PeopleCert often tests the distinction between the roles responsible for defining quality criteria (Senior User) versus those responsible for performing quality activities (Project Manager) or providing independent assurance (Project Assurance), leading candidates to confuse the 'doing' with the 'owning' of quality.

How to eliminate wrong answers

Option A is wrong because the Project Manager is responsible for managing the project on a day-to-day basis and ensuring that quality management activities are performed, but not for defining or verifying the quality criteria themselves. Option C is wrong because Project Assurance provides independent oversight and checks that the project is being conducted correctly, but it does not own the quality criteria for the products. Option D is wrong because the Senior Supplier is responsible for providing the resources and expertise to create the products, not for defining or verifying the quality criteria that the products must meet.

331
MCQeasy

Which role is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (SRO/Executive)
B.Senior User
C.Project Assurance
D.Project Manager
AnswerA

The SRO owns the Business Case and is accountable for its viability throughout the project.

Why this answer

The Senior Responsible Owner (SRO/Executive) is accountable for the Business Case and ensuring it remains viable. The Project Manager maintains it day-to-day, but the SRO owns it. This is a key PRINCE2 principle.

332
MCQeasy

In PRINCE2, which role is responsible for ensuring that the business case is maintained and that the project remains viable?

A.Senior Responsible Owner (Executive)
B.Senior Supplier
C.Senior User
D.Project Manager
AnswerA

The Executive (SRO) is accountable for the business case and its viability.

Why this answer

The Senior Responsible Owner (SRO/Executive) is accountable for the business case and its ongoing viability throughout the project.

333
MCQhard

What is the difference between the Senior Responsible Owner (SRO/Executive) and a Project Sponsor?

A.The SRO is a member of the Project Board; the Sponsor is not
B.The SRO is a PRINCE2 role; 'Project Sponsor' is not a PRINCE2 term
C.They are the same role with different names
D.The Project Sponsor is more senior than the SRO
AnswerB

PRINCE2 uses SRO, not sponsor.

Why this answer

Option B is correct because PRINCE2 defines the Senior Responsible Owner (SRO) as the single person accountable for the business case and overall project success, and it is a formal role within the PRINCE2 Project Board. 'Project Sponsor' is a generic term used in many organizations but is not a defined role in the PRINCE2 methodology. Therefore, the key difference is that the SRO is a specific PRINCE2 role, while 'Project Sponsor' is not part of the PRINCE2 terminology.

Exam trap

The trap here is that many candidates assume 'Project Sponsor' is a standard PRINCE2 role because it is widely used in industry, but PRINCE2 specifically uses 'Senior Responsible Owner' (or 'Executive') and does not include 'Project Sponsor' in its role definitions, making option B the only technically accurate answer.

How to eliminate wrong answers

Option A is wrong because in PRINCE2, the SRO (Executive) is indeed a member of the Project Board, but the statement that the Sponsor is not a member is misleading—'Project Sponsor' is not a PRINCE2 term, so it cannot be evaluated as a board member within the framework. Option C is wrong because the SRO and a Project Sponsor are not the same role; the SRO is a defined PRINCE2 role with specific responsibilities (e.g., owning the business case), while 'Project Sponsor' is an ambiguous, non-PRINCE2 term that may refer to different roles in different organizations. Option D is wrong because PRINCE2 does not define a 'Project Sponsor' role, so there is no basis for comparing seniority; within PRINCE2, the SRO is the most senior role on the Project Board, but the statement implies a hierarchy that does not exist in the methodology.

334
MCQhard

In PRINCE2, what is the key difference between Project Assurance and a quality review?

A.Project Assurance ensures quality; quality review ensures business case viability
B.There is no difference; they are the same thing
C.Project Assurance is performed by the Project Manager; quality review is performed by the team
D.Project Assurance is a role; quality review is a technique
AnswerD

Project Assurance is a defined role in the project management team; quality review is a technique for product evaluation.

Why this answer

Project Assurance is a role within the PRINCE2 management structure, responsible for monitoring all aspects of the project's performance and products independently of the Project Manager. A quality review, on the other hand, is a specific technique used to assess the quality of a product against its defined quality criteria. Therefore, the key difference is that one is a role and the other is a technique.

Exam trap

The trap here is confusing a role (Project Assurance) with a technique (quality review), as both involve checking quality, but PRINCE2 explicitly separates them into different components of the management system.

How to eliminate wrong answers

Option A is wrong because Project Assurance ensures that the project is being conducted properly across all management themes (including business case viability), not just quality, while a quality review is a technique focused on product quality, not business case viability. Option B is wrong because Project Assurance and a quality review are fundamentally different concepts: one is a role (who does it) and the other is a technique (how it is done). Option C is wrong because Project Assurance is performed by individuals independent of the Project Manager (often from the Project Board or external), not by the Project Manager, and a quality review is performed by a review team that includes the producer, reviewers, and a chair, not solely by the team.

335
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To control the work of the current stage
B.To close the project after a stage has been completed
C.To enable the Project Board to review the stage just completed and authorize the next stage
D.To plan the initiation stage
AnswerC

This is the correct purpose of Managing a Stage Boundary.

Why this answer

The purpose is to provide the Project Board with information to review the current stage, approve the next stage plan, and update the project plan and Business Case. Option C is correct.

← PreviousPage 5 of 5 · 335 questions total

Ready to test yourself?

Try a timed practice session using only Prince2 People questions.