Question 1,620 of 1,731
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is the Project Manager. This is correct because, within the PRINCE2 methodology, the Project Manager holds the responsibility for producing the Highlight Report to provide the Project Board with a concise summary of progress against the stage plan, including any issues, risks, and forecasts for the next reporting period. The frequency of these reports is defined in the Communication Management Strategy, ensuring the board remains informed without being overwhelmed by detail. On the PRINCE2 Foundation exam, this question tests your understanding of role-specific accountabilities versus management products; a common trap is confusing the Project Manager with the Project Support office, which may assist with data collection but does not own the report. To remember this, think of the Highlight Report as the Project Manager’s “status update” to the board—the manager prepares it, the board receives it.

PRINCE2F People: organizations, teams, and leadership Practice Question

This PRINCE2F practice question tests your understanding of people: organizations, teams, and leadership. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which role is responsible for producing the Highlight Report?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

The Highlight Report is a progress report that summarizes the status of a management stage for the Project Board. According to PRINCE2, the Project Manager is responsible for producing the Highlight Report at intervals defined in the Communication Management Strategy, typically to keep the Project Board informed of progress, exceptions, and forecasts.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Support

    Why it's wrong here

    Project Support may assist but does not produce the Highlight Report.

  • Project Manager

    Why this is correct

    The PM produces the Highlight Report.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Senior Responsible Owner

    Why it's wrong here

    The SRO receives the Highlight Report but does not produce it.

  • Team Manager

    Why it's wrong here

    Team Managers produce Checkpoint Reports.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the Highlight Report with the Checkpoint Report, mistakenly assigning the Team Manager as the producer, when in fact the Team Manager produces the Checkpoint Report and the Project Manager produces the Highlight Report.

Detailed technical explanation

How to think about this question

The Highlight Report is a key input to the Managing a Stage Boundary process and is also used in the Directing a Project process to enable the Project Board to assess whether the stage is on track. It includes actual versus planned progress, forecast completion dates, and any issues or risks. In PRINCE2, the frequency of Highlight Reports is defined in the Communication Management Strategy, and the Project Manager must ensure the report aligns with the management stage tolerances.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

People: organizations, teams, and leadership — This question tests People: organizations, teams, and leadership — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Project Manager — The Highlight Report is a progress report that summarizes the status of a management stage for the Project Board. According to PRINCE2, the Project Manager is responsible for producing the Highlight Report at intervals defined in the Communication Management Strategy, typically to keep the Project Board informed of progress, exceptions, and forecasts.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In PRINCE2, who is responsible for preparing and updating the Highlight Report?

medium
  • A.Team Manager
  • B.Project Support
  • C.Project Manager
  • D.Senior User

Why C: The Project Manager prepares the Highlight Report and sends it to the Project Board at regular intervals (e.g., weekly or monthly) to provide a summary of stage status.

Variation 2. Which role is responsible for preparing the Highlight Report?

easy
  • A.Project Support
  • B.Team Manager
  • C.Project Manager
  • D.Senior User

Why C: The Highlight Report is prepared by the Project Manager and sent to the Project Board at intervals defined in the Communication Management Approach.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.