PRINCE2F People: organizations, teams, and leadership Practice Question
Which THREE of the following are elements of the PRINCE2 project management team?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
The PRINCE2 project management team includes the Project Board (Executive, Senior User, Senior Supplier), Project Manager, Team Manager, and optionally Project Assurance and Project Support. User group and Steering Committee are not PRINCE2 terms.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Board
Why this is correct
Correct: The Project Board is the top-level decision-making body.
- ✓
Team Manager
Why this is correct
Correct: The Team Manager delivers Work Packages.
- ✓
Project Manager
Why this is correct
Correct: The Project Manager runs the project day-to-day.
- ✗
User Group
Why it's wrong here
Not a PRINCE2 role.
- ✗
Steering Committee
Why it's wrong here
PRINCE2 uses the term Project Board, not Steering Committee.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.