Question 1,582 of 1,731
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is the Team Manager. This is correct because in PRINCE2, the work package delivery responsibility rests solely with the Team Manager, who is appointed by the Project Manager to coordinate the technical work and ensure the products within the work package meet the agreed quality criteria and are delivered on time. During the Controlling a Stage process, the Project Manager authorizes the work package, but the actual execution and delivery are delegated to the Team Manager, who then reports progress and completion back to the Project Manager. On the PRINCE2 Foundation exam, this question tests your understanding of role boundaries within the project management team, often appearing as a trap where candidates mistakenly assign delivery to the Project Manager or the team members directly. A common memory tip is to remember that the Project Manager "authorizes" the work, but the Team Manager "delivers" it—think of the "T" in Team Manager standing for "Takes the work to the team."

PRINCE2F People: organizations, teams, and leadership Practice Question

This PRINCE2F practice question tests your understanding of people: organizations, teams, and leadership. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During the Controlling a Stage process, a Work Package is authorized by the Project Manager. Who is responsible for delivering the Work Package?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Team Manager

In PRINCE2, the Team Manager is the role responsible for delivering the Work Package authorized by the Project Manager during the Controlling a Stage process. The Team Manager coordinates the team's work, ensures the products meet the agreed quality criteria, and reports progress back to the Project Manager.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Supplier

    Why it's wrong here

    The Senior Supplier provides resources but is not directly responsible for delivery.

  • Project Support

    Why it's wrong here

    Project Support provides administrative assistance, not delivery.

  • Team Manager

    Why this is correct

    Correct: The Team Manager manages the work and delivers the Work Package.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Project Manager

    Why it's wrong here

    The Project Manager authorizes the Work Package and manages the stage, but delivery is done by the team.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the Project Manager's role of authorizing the Work Package with the responsibility for its delivery, leading them to select the Project Manager instead of the Team Manager.

Detailed technical explanation

How to think about this question

The Work Package is a key management product that defines the scope, quality criteria, and reporting requirements for a set of products. The Team Manager uses the Work Package to plan and control the team's work, and must escalate any deviations via the 'Checkpoint Report' to the Project Manager. In a real-world scenario, if the Work Package involves developing a software module, the Team Manager would assign tasks to developers, track progress, and ensure the module meets the acceptance criteria before handing it back.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

People: organizations, teams, and leadership — This question tests People: organizations, teams, and leadership — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Team Manager — In PRINCE2, the Team Manager is the role responsible for delivering the Work Package authorized by the Project Manager during the Controlling a Stage process. The Team Manager coordinates the team's work, ensures the products meet the agreed quality criteria, and reports progress back to the Project Manager.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.