Which THREE of the following are responsibilities of the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Defining project tolerances
The Project Board is responsible for strategic decisions: approving plans, defining tolerances, and authorizing stage boundaries. Day-to-day management is the PM's role.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Defining project tolerances
Why this is correct
The Project Board sets tolerances for the project.
- ✗
Preparing the Highlight Report
Why it's wrong here
The Project Manager prepares the Highlight Report.
- ✓
Authorizing the start of each management stage
Why this is correct
The Board authorizes stage boundaries.
- ✓
Approving the Project Plan
Why this is correct
The Project Board approves the Project Plan.
- ✗
Managing the team's day-to-day activities
Why it's wrong here
Team management is the responsibility of the Team Manager or Project Manager.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.