In PRINCE2, which role is responsible for ensuring that the business case is maintained and that the project remains viable?

⚠ Common exam trap

It's easy for candidates to confuse the Project Manager's responsibility for day-to-day management with the Executive's accountability for the business case, leading them to incorrectly select the Project Manager as the owner of business viability.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior Responsible Owner (Executive)

The Senior Responsible Owner (Executive) is the single person accountable for the business case and for ensuring that the project remains viable throughout its lifecycle. They own the business justification and have the authority to stop the project if it no longer meets the organization's objectives or if the costs outweigh the benefits.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Responsible Owner (Executive)

    Why this is correct

    The Executive (SRO) is accountable for the business case and its viability.

  • Senior Supplier

    Why it's wrong here

    The Senior Supplier represents the supplier interests but does not own the business case.

  • Senior User

    Why it's wrong here

    The Senior User represents the users' interests but is not responsible for the business case.

  • Project Manager

    Why it's wrong here

    The Project Manager manages the day-to-day work but does not own the business case.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

5 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In PRINCE2, who is responsible for maintaining the Business Case throughout the project?

easy
  • A.Senior Responsible Owner (Executive)
  • B.Project Manager
  • C.Senior Supplier
  • D.Project Assurance

Why B: In PRINCE2, the Project Manager is responsible for maintaining the Business Case on a day-to-day basis. This includes monitoring actual benefits against the expected benefits, updating the Business Case with any changes, and reporting to the Project Board. The Executive is accountable for the Business Case and makes decisions based on its viability, but the Project Manager handles the maintenance activities.

Variation 2. Which role is responsible for maintaining the Business Case throughout the project?

easy
  • A.Project Manager
  • B.Senior User
  • C.Executive (Senior Responsible Owner)
  • D.Project Assurance

Why C: The Executive (Senior Responsible Owner) is accountable for the Business Case and its maintenance throughout the project. The Project Manager develops and maintains the Business Case on behalf of the Executive, but accountability rests with the Executive.

Variation 3. Which role is responsible for maintaining the Business Case throughout the project?

easy
  • A.Senior Responsible Owner (Executive)
  • B.Project Assurance
  • C.Project Manager
  • D.Senior User

Why A: The Senior Responsible Owner (SRO/Executive) owns the Business Case and is accountable for ensuring it remains viable. The Project Manager maintains the Business Case on behalf of the Executive.

Variation 4. Which role is responsible for maintaining the Business Case throughout the project?

easy
  • A.Senior Supplier
  • B.Project Manager
  • C.Senior User
  • D.Executive (Senior Responsible Owner)

Why D: The Executive (Senior Responsible Owner) is accountable for the Business Case and ensuring it remains viable. The Project Manager maintains it on a day-to-day basis, but the Executive holds ultimate responsibility.

Variation 5. Which role is responsible for maintaining the Business Case throughout the project?

easy
  • A.Senior Responsible Owner (SRO/Executive)
  • B.Senior User
  • C.Project Assurance
  • D.Project Manager

Why A: The Senior Responsible Owner (SRO/Executive) is accountable for the Business Case and ensuring it remains viable. The Project Manager maintains it day-to-day, but the SRO owns it. This is a key PRINCE2 principle.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.