- A
Wait until the next stage to address the risk
Why wrong: Proactive risk management is required; waiting is not PRINCE2 best practice.
- B
Update the Project Plan to include the risk
Why wrong: Risks are recorded in the Risk Register, not the Project Plan.
- C
Update the Risk Register and manage the risk as part of the current stage
Correct. Risks should be recorded and managed as they are identified, even if impact is in the future.
- D
Raise an Exception Report to the Project Board
Why wrong: An Exception Report is for when tolerances are forecast to be breached, not for new risks.
Quick Answer
The answer is to update the Risk Register and manage the risk as part of the current stage. This is correct because, under PRINCE2, the Project Manager owns the risk management process and must formally record any newly identified risk in the Risk Register, regardless of when it might materialize. Even though the risk could impact the next stage, the Project Manager’s immediate duty is to capture it now and manage it within the current stage’s control, rather than deferring it. On the PRINCE2 Foundation exam, this question tests your understanding of the Project Manager’s responsibility for continuous risk management versus the Team Manager’s role in identifying issues. A common trap is thinking the risk should wait for the next stage plan or be escalated to the Project Board immediately; the Highlight Report is for stage progress, not risk escalation. Remember the mnemonic: “Record now, manage later” — always log a risk the moment it surfaces.
PRINCE2F PRINCE2 Processes Practice Question
This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
The Project Board receives a Highlight Report indicating that the stage is on track. However, a Team Manager has identified a potential risk that could impact the next stage. What should the Project Manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Update the Risk Register and manage the risk as part of the current stage
Risks are managed by the Project Manager. The risk should be added to the Risk Register and monitored. The Highlight Report is for reporting current stage progress; the risk can be mentioned but the immediate action is to record it.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Wait until the next stage to address the risk
Why it's wrong here
Proactive risk management is required; waiting is not PRINCE2 best practice.
- ✗
Update the Project Plan to include the risk
Why it's wrong here
Risks are recorded in the Risk Register, not the Project Plan.
- ✓
Update the Risk Register and manage the risk as part of the current stage
Why this is correct
Correct. Risks should be recorded and managed as they are identified, even if impact is in the future.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Raise an Exception Report to the Project Board
Why it's wrong here
An Exception Report is for when tolerances are forecast to be breached, not for new risks.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PRINCE2F exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
PRINCE2 Processes — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Processes practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Update the Risk Register and manage the risk as part of the current stage — Risks are managed by the Project Manager. The risk should be added to the Risk Register and monitored. The Highlight Report is for reporting current stage progress; the risk can be mentioned but the immediate action is to record it.
What should I do if I get this PRINCE2F question wrong?
Identify which PRINCE2F exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 21, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.