- A
Senior User
Why wrong: The senior user represents user interests, not the business case.
- B
Senior Supplier
Why wrong: The senior supplier provides resources, not ownership of the business case.
- C
Executive
The executive owns the business case.
- D
Project Manager
Why wrong: The project manager manages the project but does not own the business case.
Quick Answer
The answer is the Executive. This role is correct because the Executive is the single individual who owns the business case and is ultimately accountable for the project's justification, making them responsible for ensuring its viability from initiation through closure. In the PRINCE2 Business Case theme, the Executive must continuously assess whether the project remains desirable, viable, and achievable, approving any changes that could alter the business justification. On the PRINCE2 Foundation exam, this question tests your understanding of accountability versus responsibility—a common trap is confusing the Executive with the Senior User or Project Manager, who support viability but do not own it. Remember the mnemonic "Executive Equals Endorsement": the Executive endorses every stage that the business case remains sound.
PRINCE2F Business Case and Organizing Practice Question
This PRINCE2F practice question tests your understanding of business case and organizing. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which role is responsible for ensuring that the project's business case remains viable throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Executive
The Executive is the single individual who owns the business case and is ultimately accountable for the project's justification. Throughout the project, the Executive must ensure that the business case remains viable, approving any changes that affect its justification. This is a core responsibility defined in the PRINCE2 Business Case theme.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior User
Why it's wrong here
The senior user represents user interests, not the business case.
- ✗
Senior Supplier
Why it's wrong here
The senior supplier provides resources, not ownership of the business case.
- ✓
Executive
Why this is correct
The executive owns the business case.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Project Manager
Why it's wrong here
The project manager manages the project but does not own the business case.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PeopleCert often tests the misconception that the Project Manager is responsible for the business case's viability, but the Executive is the owner and decision-maker for the business case, while the Project Manager only manages its development and updates.
Detailed technical explanation
How to think about this question
The Business Case is developed iteratively; the Executive must formally review it at each stage boundary and at the end of each management stage. If the business case becomes unviable (e.g., costs exceed benefits), the Executive has the authority to prematurely close the project. This is enforced through the PRINCE2 principle of continued business justification, which mandates that the project must remain desirable, viable, and achievable.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Business Case and Organizing — study guide chapter
Learn the concepts, then practise the questions
- →
Business Case and Organizing practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
Business Case and Organizing — This question tests Business Case and Organizing — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Executive — The Executive is the single individual who owns the business case and is ultimately accountable for the project's justification. Throughout the project, the Executive must ensure that the business case remains viable, approving any changes that affect its justification. This is a core responsibility defined in the PRINCE2 Business Case theme.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
4 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute for the executive when making business case decisions?
medium- ✓ A.No role can substitute; the project should be escalated to the project board
- B.Senior User
- C.Senior Supplier
- D.Project Assurance
Why A: In PRINCE2, the Executive is the single point of accountability for the business case and must approve any changes to it. If the Executive is unavailable, no other role can substitute for this authority; the project manager must escalate the decision to the full Project Board. This ensures that business justification decisions are never made without the accountable party or the collective board.
Variation 2. During a project, the cost-benefit ratio becomes unfavorable. What is the first action the project manager should take?
hard- A.Update the Business Case without informing the board
- B.Reduce project scope to cut costs
- C.Stop the project immediately
- ✓ D.Request a formal review of the Business Case by the project board
Why D: In PRINCE2, the Business Case is the key document for justifying the project's continued viability. When the cost-benefit ratio becomes unfavorable, the project manager must escalate this issue to the project board, which holds the authority to approve changes to the Business Case or decide on project continuation. Option D is correct because the project manager's first action is to request a formal review by the project board, as per the 'continued business justification' principle and the 'manage by stages' theme.
Variation 3. You are the project manager for a software development project. The business case shows a net present value (NPV) of $200,000 with a payback period of 18 months. During the initiating stage, the senior supplier informs you that the cost of a key component has increased by 20%, which will reduce the NPV to $50,000 and extend the payback period to 24 months. The project board is not scheduled to meet for another month. What should you do?
medium- ✓ A.Request an extraordinary meeting of the project board to discuss the revised business case
- B.Update the business case with the new figures and continue with the project
- C.Reduce project scope to bring costs back in line with the original business case
- D.Wait for the next scheduled board meeting to present the changes
Why A: The correct answer is A because PRINCE2 requires that any change to the business case, especially one that significantly reduces NPV and extends payback period, must be escalated to the project board for a decision. As project manager, you cannot unilaterally update the business case or change scope; you must request an extraordinary meeting to present the revised business case and seek approval to continue. This aligns with the 'continued business justification' principle and the 'manage by stages' theme.
Variation 4. During a project, the senior user requests a change that significantly increases benefits but also increases costs. What should the project manager do first?
hard- A.Implement the change immediately to realize benefits quickly
- B.Update the Business Case and proceed without approval
- C.Reject the change because it increases costs
- ✓ D.Assess the impact on the Business Case and submit a change request to the project board
Why D: In PRINCE2, any change that impacts the Business Case must be formally assessed before action is taken. The project manager's first responsibility is to evaluate the change's effect on the Business Case (costs vs. benefits) and then submit a formal change request to the Project Board, which holds authority for approving changes that alter the project's justification. Option D aligns with the 'manage by stages' and 'continued business justification' principles.
Last reviewed: Jun 30, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.