Question 1,574 of 1,731
Project Initiation and StageshardMultiple ChoiceObjective-mapped

Quick Answer

The correct answer is to update the Business Case with risk-adjusted benefits and present it to the board. This is because the PRINCE2 principle of continued business justification demands that the Business Case remain viable throughout the project, especially during Initiation when key decisions are made. By factoring in the 30% risk from market volatility, the expected benefits drop to £910,000, which is below the £1.2 million cost, making the project unviable on a risk-adjusted basis. On the PRINCE2 Foundation exam, this scenario tests your understanding that the Business Case is a living document and must reflect current risks, not just initial estimates. A common trap is to proceed with the original optimistic figures or to ignore the risk quantification. Remember the memory tip: "Risk-adjust or reject"—if a risk materially changes the cost-benefit ratio, you must update the Business Case before the board can approve initiation.

PRINCE2F Project Initiation and Stages Practice Question

This PRINCE2F practice question tests your understanding of project initiation and stages. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are the project manager for a software implementation project in a large retail company. The project is currently in the Initiation Stage. The senior user has provided the requirements, and the senior supplier has estimated that the project will cost £1.2 million and take 18 months. However, during a review of the Business Case, you discover that the expected benefits are only £1.3 million, giving a benefit-cost ratio of just 1.08:1. Additionally, the market conditions are volatile, and there is a risk that a competitor may launch a similar product before your project completes, potentially reducing benefits by 30%. The project board is eager to proceed but wants assurance that the project is viable. What should you do?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the Business Case with risk-adjusted benefits and present to the board

Option D is correct because the PRINCE2 principle of continued business justification requires that the Business Case be updated to reflect current risks and uncertainties. In this scenario, the market volatility and competitor risk could reduce benefits by 30%, dropping the expected benefits to £910,000, which is below the £1.2 million cost, making the project unviable. Presenting this risk-adjusted Business Case to the board allows them to make an informed decision on whether to proceed, rather than proceeding with an overly optimistic view.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Proceed with the current Business Case as the board is eager

    Why it's wrong here

    Ignoring risks is not prudent; the board needs full information.

  • Escalate to the programme manager without updating the Business Case

    Why it's wrong here

    The PM should first assess and update the Business Case.

  • Recommend cancelling the project due to poor viability

    Why it's wrong here

    Too premature; the risk-adjusted case may still be acceptable.

  • Update the Business Case with risk-adjusted benefits and present to the board

    Why this is correct

    This provides a realistic assessment for decision-making.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may think the board's eagerness (Option A) or escalation (Option B) is sufficient, but PRINCE2 requires the Business Case to be updated with risk-adjusted figures before any decision is made, ensuring continued business justification.

Detailed technical explanation

How to think about this question

In PRINCE2, the Business Case is a living document that must be updated throughout the project, especially when new risks or changes in assumptions occur. The risk-adjusted benefits calculation involves applying the probability and impact of risks to the expected benefits; here, a 30% reduction due to competitor launch would reduce benefits from £1.3M to £910K, making the benefit-cost ratio 0.76:1, which is below the threshold for viability. This aligns with the PRINCE2 requirement that the project must remain desirable (benefits outweigh costs), viable (achievable), and achievable (feasible) throughout its lifecycle.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

Project Initiation and Stages — This question tests Project Initiation and Stages — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Update the Business Case with risk-adjusted benefits and present to the board — Option D is correct because the PRINCE2 principle of continued business justification requires that the Business Case be updated to reflect current risks and uncertainties. In this scenario, the market volatility and competitor risk could reduce benefits by 30%, dropping the expected benefits to £910,000, which is below the £1.2 million cost, making the project unviable. Presenting this risk-adjusted Business Case to the board allows them to make an informed decision on whether to proceed, rather than proceeding with an overly optimistic view.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During Initiation, the project manager discovers that a key assumption in the Business Case is invalid. What should the PM do first?

hard
  • A.Ignore the assumption
  • B.Stop the project
  • C.Inform the Project Board
  • D.Update the Business Case

Why D: The Business Case is the key driver for the project, and if a fundamental assumption is invalid, the project manager must first update the Business Case to reflect the new reality. This ensures that the project remains viable and that the Project Board can make an informed decision about whether to continue. Updating the Business Case is the correct first step because it provides the basis for any subsequent decisions, such as escalating to the Project Board.

Variation 2. A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What should the project manager do?

hard
  • A.Reduce scope to lower costs
  • B.Seek alternative options to improve benefits
  • C.Provide justification and request approval
  • D.Recommend project cancellation

Why C: The Business Case shows a cost-benefit ratio of 1:1.2, which is positive (benefits exceed costs). The project board's concern does not automatically invalidate the Business Case. According to PRINCE2, the project manager's role during initiation is to provide the board with the justification (the Business Case) and formally request approval to proceed. Option C is correct because the project manager must present the evidence and seek a decision, not unilaterally change scope or cancel.

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.