CCNA PRINCE2 Processes Questions

52 of 502 questions · Page 7/7 · PRINCE2 Processes · Answers revealed

451
MCQmedium

The Project Board has authorized a Stage Plan. During the stage, the Project Manager identifies a risk that could cause the stage to exceed its time tolerance. What should the Project Manager do first?

A.Inform the Team Manager to accelerate work to stay within tolerance
B.Raise an Exception Report to the Project Board and await their direction
C.Record the risk in the Risk Register and continue monitoring
D.Implement a contingency plan to mitigate the risk and continue as planned
AnswerB

When a stage tolerance is forecast to be exceeded, the PM must escalate via an Exception Report to the Project Board.

Why this answer

According to PRINCE2's management by exception, if a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The PM cannot unilaterally change the plan.

452
Multi-Selectmedium

Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?

Select 3 answers
A.Approving stage plans and updates
B.Producing Checkpoint Reports
C.Managing the day-to-day activities of the project team
D.Authorising closure of the project
E.Authorising initiation of the project
AnswersA, D, E

The Board approves stage plans and Exception Plans.

Why this answer

Option A is correct because the Project Board is responsible for approving Stage Plans and any updates to them during the Directing a Project process. This ensures that the project remains aligned with the business case and that management stage boundaries are properly controlled.

Exam trap

PeopleCert often tests the distinction between strategic and operational responsibilities, so the trap here is confusing the Project Board's high-level decision-making role with the Project Manager's or Team Manager's execution-level duties.

453
MCQhard

A Team Manager identifies a quality problem in a product that is being delivered. What should the Team Manager do?

A.Record the problem and inform the Project Manager
B.Update the Checkpoint Report and ignore the problem
C.Reject the product and stop all work
D.Fix the product immediately to meet quality criteria
AnswerA

The Team Manager should raise an issue and escalate to the Project Manager for a decision.

Why this answer

The Team Manager should first record the quality problem as an issue and escalate it to the Project Manager, who will decide how to handle it. The Team Manager cannot unilaterally change the product or stop work without authorization.

454
MCQmedium

In which process are Work Packages authorized and progress reviewed by the Project Manager?

A.Directing a Project
B.Controlling a Stage
C.Managing a Stage Boundary
D.Managing Product Delivery
AnswerB

Correct: CS includes authorizing and reviewing Work Packages.

Why this answer

Controlling a Stage (CS) is where the PM authorizes Work Packages, monitors progress, and takes corrective action.

455
MCQmedium

Which process ensures that the project's products are formally handed over to the operational environment?

A.Controlling a Stage
B.Directing a Project
C.Closing a Project
D.Managing Product Delivery
AnswerC

Correct. CP handles the formal closure and handover.

Why this answer

Closing a Project ensures controlled closure, including handover of products, confirmation of benefits review arrangements, and release of resources.

456
MCQmedium

Which process is responsible for producing the End Project Report?

A.Closing a Project
B.Initiating a Project
C.Directing a Project
D.Managing a Stage Boundary
AnswerA

CP produces the End Project Report as part of the closure activities.

Why this answer

The Closing a Project process produces the End Project Report, which assesses how the project performed against its plan and justifies closure.

457
Multi-Selectmedium

Which TWO of the following are outputs of the Starting Up a Project process?

Select 2 answers
A.Project Brief
B.Benefits Management Approach
C.Project Initiation Documentation
D.Daily Log
E.End Stage Report
AnswersA, D

Why this answer

Starting Up a Project produces the Project Brief, Initiation Stage Plan, and Daily Log. PID and Benefits Management Approach are from Initiating a Project. End Stage Report is from Managing a Stage Boundary.

458
MCQeasy

What is the purpose of the Closing a Project process?

A.To ensure the project is closed in a controlled way
B.To plan the next stage of the project
C.To authorize the start of the project
D.To manage day-to-day activities in a stage
AnswerA

Correct. Closing a Project provides controlled closure.

Why this answer

Closing a Project ensures a controlled closure, handover of products, evaluation of the project, and recommendations for future projects.

459
MCQmedium

The Project Manager has produced an End Stage Report for the current stage. According to PRINCE2, what is the next step?

A.Update the Business Case and close the project
B.Distribute the report to stakeholders and continue to the next stage
C.Seek approval from the Executive to continue
D.Submit the report to the Project Board for a decision on whether to proceed
AnswerD

Why this answer

The End Stage Report is submitted to the Project Board as part of Managing a Stage Boundary. The Project Board decides whether to authorise the next stage. Options A and D bypass the full board.

C is for Closing a Project.

460
MCQmedium

During the Managing Product Delivery process, a Team Manager discovers that a product cannot meet its quality criteria without significant extra work. What should the Team Manager do?

A.Modify the quality criteria to match what can be achieved
B.Raise an issue to the Project Manager for direction
C.Proceed with the work and report the variance in the next Checkpoint Report
D.Inform the Project Board directly
AnswerB

The Team Manager should raise an issue to the PM, who will decide on corrective action or change.

Why this answer

If a product cannot meet its quality criteria, the Team Manager must escalate the issue to the Project Manager as an issue, following the issue and change control procedure.

461
Multi-Selectmedium

Which TWO documents are produced during the Closing a Project process?

Select 2 answers
A.Project Brief
B.Lessons Report
C.Stage Plan
D.End Project Report
E.Project Initiation Documentation (PID)
AnswersB, D

Correct: The Lessons Report is produced in CP.

Why this answer

The End Project Report and the Lessons Report are both produced in CP. The Project Brief is from SU, the PID from IP, and the Stage Plan from SB.

462
MCQmedium

In which process are the Project Board's key decisions made, such as authorizing initiation and authorizing stage plans?

A.Starting Up a Project
B.Directing a Project
C.Initiating a Project
D.Controlling a Stage
AnswerB

Correct. DP is the Project Board's process for direction and authorization.

Why this answer

Directing a Project is the process where the Project Board makes key decisions, including authorizing initiation, stage plans, exception plans, and project closure.

463
MCQmedium

In which process is the End Stage Report produced?

A.Closing a Project
B.Directing a Project
C.Managing a Stage Boundary
D.Controlling a Stage
AnswerC

SB produces the End Stage Report.

Why this answer

The End Stage Report is produced during Managing a Stage Boundary (SB) to report on the current stage's performance and plan the next.

464
MCQmedium

The Project Board wants to provide ad-hoc direction to the Project Manager regarding a critical issue. Which process should the Project Board use?

A.Managing Product Delivery
B.Initiating a Project
C.Controlling a Stage
D.Directing a Project
AnswerD

Correct. Giving ad hoc direction is a key activity of DP.

Why this answer

Directing a Project includes the activity 'Giving ad hoc direction' to allow the Project Board to provide guidance or decisions outside of formal stage boundaries.

465
MCQeasy

Which process is responsible for authorizing work to be done within a stage?

A.Directing a Project
B.Controlling a Stage
C.Initiating a Project
D.Managing Product Delivery
AnswerB

The Project Manager authorizes Work Packages during Controlling a Stage.

Why this answer

In Controlling a Stage, the Project Manager authorizes Work Packages, but the authorization to proceed with the stage comes from the Project Board via Directing a Project.

466
MCQhard

Which process is the Project Board primarily responsible for, according to PRINCE2?

A.Directing a Project
B.Managing Product Delivery
C.Controlling a Stage
D.Managing a Stage Boundary
AnswerA

Why this answer

Directing a Project is the process that covers the Project Board's activities: authorising initiation, project, stages, exception plans, and closure. The Project Board does not manage day-to-day work.

467
Multi-Selecthard

Which TWO of the following activities are performed in the Starting Up a Project process?

Select 2 answers
A.Appoint the Executive and the Project Manager
B.Produce the Project Initiation Documentation
C.Authorise the project
D.Plan the next management stage
E.Capture lessons from previous projects
AnswersA, E

SU includes appointing the Executive and PM.

Why this answer

Starting Up a Project includes appointing the Executive and Project Manager, and capturing lessons from previous projects. Authorising the project is done in Directing a Project. Producing the PID is done in Initiating a Project.

Planning the next stage is done in Managing a Stage Boundary.

468
MCQeasy

What is the purpose of the Starting Up a Project process?

A.To plan the entire project in detail
B.To produce the Project Initiation Documentation
C.To ensure that there is a viable and worthwhile project before committing to a full initiation
D.To approve the project mandate
AnswerC

SU's purpose is to check viability before initiating.

Why this answer

The Starting Up a Project process is designed to evaluate the project mandate and determine whether the project is viable and worthwhile before committing significant resources to full initiation. It ensures that the project has a clear business justification, a defined project manager, and a sufficient understanding of scope and risks to proceed. This process does not produce detailed plans or the Project Initiation Documentation (PID), which are outputs of the Initiating a Project process.

Exam trap

PeopleCert often tests the distinction between pre-initiation and initiation activities, trapping candidates who confuse the creation of the Project Initiation Documentation (PID) with the Starting Up a Project process, when in fact the PID is a product of the Initiating a Project process.

How to eliminate wrong answers

Option A is wrong because the Starting Up a Project process only creates outline plans (e.g., a stage plan for initiation), not a detailed plan for the entire project; detailed planning occurs during the Initiating a Project process. Option B is wrong because the Project Initiation Documentation (PID) is produced during the Initiating a Project process, not during Starting Up a Project, which focuses on pre-initiation checks. Option D is wrong because the project mandate is an input to the Starting Up a Project process, not an output to be approved; the process evaluates the mandate to decide whether to proceed to initiation.

469
MCQmedium

A project is in its final stage. The Project Manager has verified that all products have been accepted and operational support is in place. Which process should the Project Manager initiate next?

A.Closing a Project
B.Controlling a Stage
C.Directing a Project
D.Managing a Stage Boundary
AnswerA

Correct. The Project Manager performs Closing a Project to prepare for project closure.

Why this answer

Closing a Project is the process for controlled closure, including handover, benefits review planning, and project closure recommendation.

470
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable
B.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
AnswerC

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report. This is management by exception.

Why this answer

Option C is correct. When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally decide to exceed tolerances; that requires Project Board authorisation.

Option A is wrong because the PM cannot increase the budget without Project Board approval. Option B is wrong because continuing without escalation violates management by exception. Option D is wrong because closing the project is not the appropriate response to a stage tolerance breach.

471
Drag & Dropmedium

Drag and drop the steps to manage a configuration item in PRINCE2 into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order

Why this order

Configuration management: identify, control changes, record status, verify, and report.

472
MCQmedium

The project manager notices that a team member has not completed a critical product according to the quality criteria. What should the project manager do first?

A.Update the Project Plan to reflect the delay
B.Close the project as the quality criteria are not met
C.Raise an Exception Report to the Project Board
D.Instruct the team manager to correct the product within the work package tolerance
AnswerD

Correct. The PM should manage the issue within the stage; the team manager can take corrective action.

Why this answer

The PM should first assess whether this is an issue that can be resolved within the stage's tolerances. If it cannot, an escalation is needed. But initially, corrective action within CS is appropriate.

473
MCQmedium

During the Initiating a Project process, which document details how quality will be managed on the project?

A.Risk Management Approach
B.Business Case
C.Quality Management Approach
D.Project Plan
AnswerC

This document describes how quality will be managed throughout the project.

Why this answer

The Quality Management Approach is one of the management approaches produced in IP, defining quality procedures and standards.

474
MCQhard

A project is in the Initiating a Project process. Which management product is defined as the key output of this process?

A.End Project Report
B.Benefits Review Plan
C.Project Brief
D.Project Initiation Documentation
AnswerD

Correct. The PID is the definitive document created during IP.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It provides a solid foundation for the project.

475
MCQeasy

Which process is responsible for authorizing a Work Package?

A.Managing Product Delivery
B.Managing a Stage Boundary
C.Controlling a Stage
D.Directing a Project
AnswerC

PM authorizes Work Packages in CS.

Why this answer

The Project Manager authorizes Work Packages during the Controlling a Stage process.

476
MCQhard

What is the difference between the Starting Up a Project process and the Initiating a Project process?

A.SU is for small projects; IP is for large projects
B.SU is optional; IP is mandatory
C.SU produces the Project Brief; IP produces the Project Initiation Documentation
D.SU is done by the Project Board; IP is done by the Project Manager
AnswerC

SU outputs include the Project Brief; IP outputs include the PID, which expands on the Brief.

Why this answer

SU is a pre-project process to determine if the project is viable; IP formally establishes the project foundation and produces the PID.

477
MCQhard

A project is in the Controlling a Stage process, and the Project Manager receives a Request for Change (RFC) from a stakeholder. What should the Project Manager do first?

A.Implement the change immediately to satisfy the stakeholder
B.Log the issue in the Issue Register
C.Escalate directly to the Project Board
D.Reject the change as it was not planned
AnswerB

The first step is to record the RFC in the Issue Register, then analyze and decide.

Why this answer

All changes must be logged in the Issue Register before analysis. The Project Manager then assesses the impact and may escalate to the Project Board if it affects tolerances.

478
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.End Stage Report
B.Project Brief
C.Executive appointment
D.Risk Management Approach
E.Project Plan
AnswersD, E

The Risk Management Approach is part of the management strategies created in IP.

Why this answer

The Initiating a Project process produces the Project Plan (Option E) and the Risk Management Approach (Option D). The Project Plan defines the baseline for scope, schedule, and cost, while the Risk Management Approach establishes the procedures for identifying, assessing, and controlling risks throughout the project. Both are formal management products created during initiation to guide project execution.

Exam trap

The trap here is confusing the inputs and outputs of the Initiating a Project process with those of the Starting Up a Project process, particularly the Project Brief (an input) and the Executive appointment (an output of Starting Up a Project).

479
MCQmedium

In which process are End Stage Reports produced?

A.Closing a Project
B.Controlling a Stage
C.Directing a Project
D.Managing a Stage Boundary
AnswerD

SB produces End Stage Reports to inform the Project Board of progress and request authorization for the next stage.

Why this answer

End Stage Reports are produced during the Managing a Stage Boundary process, which also plans the next stage and updates the project plan.

480
MCQhard

The Project Board is considering whether to approve an Exception Plan. Which process should they use to make this decision?

A.Managing a Stage Boundary
B.Directing a Project
C.Controlling a Stage
D.Closing a Project
AnswerB

DP includes authorizing Exception Plans.

Why this answer

The Project Board makes decisions on Exception Plans as part of the Directing a Project process, specifically through the activity 'Authorize a Stage or Exception Plan'.

481
Multi-Selecteasy

Which TWO of the following are components of the Project Initiation Documentation (PID)?

Select 2 answers
A.Checkpoint Report
B.Business Case
C.End Stage Report
D.Project Plan
E.Lessons Report
AnswersB, D

Why this answer

The PID includes the Project Plan, Business Case, and various management approaches. Checkpoint Reports are from MP, End Stage Report from SB, Lessons Report from CP.

482
MCQhard

During the Controlling a Stage process, the Project Manager receives a Checkpoint Report indicating that a product will be delivered late. What should the Project Manager do first?

A.Assess the impact on stage tolerances and take corrective action if within tolerance
B.Revise the Stage Plan and inform the Project Board
C.Request a new Work Package from the Team Manager
D.Raise an Exception Report immediately
AnswerA

Correct. The PM assesses the deviation and acts accordingly; if within tolerance, they handle it; if not, they escalate.

Why this answer

If a Checkpoint Report indicates a deviation within stage tolerances, the PM can take corrective action themselves. If it threatens stage tolerance, they must escalate.

483
MCQmedium

During which process is the Business Case formally created and reviewed?

A.Initiating a Project
B.Managing a Stage Boundary
C.Starting Up a Project
D.Directing a Project
AnswerA

IP develops the full Business Case as part of the PID.

Why this answer

The Business Case is initially outlined in Starting Up a Project and fully developed in Initiating a Project, where it becomes part of the PID. It is then reviewed and updated at each stage boundary (Managing a Stage Boundary) and at project closure.

484
MCQeasy

Which process ensures that the project's products are formally accepted and the project is closed in a controlled way?

A.Closing a Project
B.Managing a Stage Boundary
C.Controlling a Stage
D.Directing a Project
AnswerA

Closing a Project ensures all products are accepted and the project is formally closed.

Why this answer

Closing a Project ensures controlled closure, product handover, and lessons learned.

485
MCQhard

Which TWO processes involve the Project Board making key authorizations? (Select two)

A.Directing a Project
B.Controlling a Stage
C.Initiating a Project
D.Starting Up a Project
E.Managing Product Delivery
AnswerA, C

DP is the Project Board's process for making key decisions and authorizations.

Why this answer

The Directing a Project process is where the Project Board authorizes the initiation of a project, authorizes stage plans, and authorizes the project closure. The Initiating a Project process includes the key authorization of the Project Initiation Documentation (PID) by the Project Board, which formally authorizes the project to proceed. Both processes involve the Project Board making critical go/no-go decisions that control the project's lifecycle.

Exam trap

PeopleCert often tests the misconception that 'Controlling a Stage' involves the Project Board, when in fact it is a Project Manager-level process, and candidates may confuse 'Starting Up a Project' with 'Initiating a Project' because both occur early in the project lifecycle.

How to eliminate wrong answers

Option B (Controlling a Stage) is wrong because this process is performed by the Project Manager, not the Project Board; it focuses on day-to-day management and reporting within a stage, not on key authorizations. Option D (Starting Up a Project) is wrong because this process is pre-project and does not involve the Project Board making authorizations; it is about assembling the project team and creating the Project Brief, with the Board only giving ad-hoc direction. Option E (Managing Product Delivery) is wrong because this process is executed by the Team Manager, who controls the work of creating products and reports to the Project Manager, not the Project Board.

486
MCQmedium

The Project Board has given ad-hoc direction to the Project Manager. In which process does this occur?

A.Managing Product Delivery
B.Directing a Project
C.Controlling a Stage
D.Starting Up a Project
AnswerB

DP includes ad-hoc direction as a key activity.

Why this answer

The 'Directing a Project' process covers the Project Board's decision-making responsibilities, including providing ad-hoc direction to the Project Manager. This process runs from project initiation to closure and is the only process where the Board gives unplanned guidance outside of stage boundaries.

Exam trap

The trap here is that candidates confuse 'Controlling a Stage' (the Project Manager's process for reporting and managing) with 'Directing a Project' (the Board's process for giving direction), because both involve communication between the Board and Project Manager, but only the latter includes ad-hoc direction.

How to eliminate wrong answers

Option A is wrong because 'Managing Product Delivery' is the process where the Team Manager accepts and executes work packages, not where the Project Board gives direction. Option C is wrong because 'Controlling a Stage' is the Project Manager's process for day-to-day management and reporting to the Board, not the Board's process for giving ad-hoc direction. Option D is wrong because 'Starting Up a Project' occurs before the Project Board is formally established and focuses on feasibility and planning, not on issuing ad-hoc directions.

487
MCQmedium

During the Closing a Project process, what is the purpose of the End Project Report?

A.To obtain approval for the next stage
B.To hand over products to the customer
C.To update the Business Case
D.To summarise project performance and lessons learned
AnswerD

The End Project Report covers performance, benefits, and lessons.

Why this answer

The End Project Report provides a final assessment of project performance against the PID, and is used to evaluate project success and inform future projects.

488
MCQmedium

Who is responsible for authorizing the initiation of a project?

A.The Senior User
B.The Project Manager
C.The Project Board
D.The Executive
AnswerC

The Project Board authorizes initiation in the Directing a Project process.

Why this answer

The Project Board, as part of the Directing a Project process, authorizes the initiation stage. The Executive chairs the Board but authorization is a Board decision.

489
MCQeasy

What is the purpose of the Closing a Project process?

A.To manage the day-to-day activities of a stage
B.To plan the next stage
C.To provide a controlled close to the project
D.To authorise the project
AnswerC

CP ensures orderly closure.

Why this answer

Closing a Project ensures controlled closure, handover of products, and confirmation of benefits review arrangements.

490
Multi-Selectmedium

Which TWO of the following are activities performed in the Directing a Project process?

Select 2 answers
A.Produce Highlight Reports
B.Authorize initiation
C.Authorize the project
D.Escalate issues to the Project Board
E.Manage product delivery
AnswersB, C

Authorizing initiation is a key decision in DP.

Why this answer

Options A and D are correct. DP includes authorizing initiation and authorizing the project. Managing product delivery is MP; escalating issues is part of CS (PM role).

491
Multi-Selectmedium

Which THREE of the following are outputs of the Initiating a Project process?

Select 3 answers
A.Project Brief
B.Quality Management Approach
C.End Stage Report
D.Business Case
E.Project Plan
AnswersB, D, E

The Quality Management Approach is one of the management approaches produced in IP.

Why this answer

The Initiating a Project process produces the Project Initiation Documentation (PID), which includes the Project Plan, Business Case, and various management approaches. The Project Brief is an output of SU, and the End Stage Report is from SB.

492
MCQeasy

Who is responsible for authorizing a Work Package?

A.Project Board
B.Project Manager
C.Team Manager
D.Executive
AnswerB

PM authorizes Work Packages as part of CS.

Why this answer

Option A is correct. The Project Manager authorizes Work Packages in Controlling a Stage.

493
Multi-Selecthard

Which THREE of the following are correct responsibilities of the Project Board in the Directing a Project process?

Select 3 answers
A.Authorise project closure
B.Authorise project initiation
C.Produce Highlight Reports
D.Give ad-hoc direction to the Project Manager
E.Manage day-to-day work of the team
AnswersA, B, D

Why this answer

The Project Board authorises initiation, gives ad-hoc direction, and authorises closure. Producing Highlight Reports is a Project Manager responsibility, and managing day-to-day work is a Team Manager responsibility.

494
MCQmedium

A project is underway, and the project manager notices that the team is frequently re-prioritizing work and losing focus. Which PRINCE2 process should the project manager use to re-establish control?

A.Managing Product Delivery
B.Managing a Stage Boundary
C.Directing a Project
D.Controlling a Stage
AnswerD

This process handles day-to-day management, including re-prioritizing work and addressing issues.

Why this answer

The project manager should use the Controlling a Stage process because it is specifically designed to monitor the day-to-day work of the stage, manage issues and risks, and take corrective action to keep the stage on track. The symptom of frequent re-prioritization and loss of focus indicates a lack of control within the current stage, which this process directly addresses by providing mechanisms for work package assignment, progress monitoring, and escalation. It ensures the stage remains within tolerance and that the team's efforts are aligned with the stage plan.

Exam trap

The trap here is that candidates confuse the day-to-day control activities of Controlling a Stage with the higher-level oversight of Directing a Project, or they mistakenly think that re-prioritization requires a stage boundary review, when in fact it is handled within the current stage.

How to eliminate wrong answers

Option A is wrong because Managing Product Delivery is the process for the team manager to accept, execute, and deliver work packages, not for the project manager to re-establish control over prioritization and focus. Option B is wrong because Managing a Stage Boundary is used at the end of a stage to plan the next stage and update the business case, not for ongoing corrective actions within a stage. Option C is wrong because Directing a Project is the process for the project board to make key decisions and provide overall direction, not for the project manager to handle day-to-day re-prioritization issues.

495
Multi-Selecthard

Which THREE of the following are activities performed in the Controlling a Stage process?

Select 3 answers
A.Create the Project Plan
B.Review progress against the Stage Plan
C.Authorize Work Packages
D.Close the project
E.Escalate issues and risks to the Project Board
AnswersB, C, E

CS includes reviewing progress.

Why this answer

CS includes activities like authorizing Work Packages, managing issues, and reviewing progress. Closing the project is CP; creating the Project Plan is IP.

496
MCQmedium

What is the purpose of the Closing a Project process?

A.To create the Lessons Report and disband the team
B.To authorize the final stage of the project
C.To ensure the project is closed in a controlled way
D.To hand over the project's products to the operational environment and review benefits
AnswerC

Correct. The purpose is to provide a controlled closure, including handover and lessons learned.

Why this answer

The purpose of Closing a Project is to provide a fixed point to verify that all project products have been accepted, confirm that the project has met its objectives, and recommend project closure.

497
MCQeasy

Which process is used by the Project Board to give ad-hoc direction to the project?

A.Managing Product Delivery
B.Controlling a Stage
C.Managing a Stage Boundary
D.Directing a Project
AnswerD

DP includes the activity 'Give ad-hoc direction'.

Why this answer

The Directing a Project process is specifically designed for the Project Board to provide overall direction and control, including making key decisions and issuing ad-hoc instructions outside of the regular stage management cycle. It covers activities like authorizing initiation, stage plans, and project closure, as well as giving ad-hoc direction to the project manager when needed.

Exam trap

PeopleCert often tests the distinction between processes owned by the Project Board (Directing a Project) versus those owned by the project manager (Controlling a Stage, Managing a Stage Boundary) to trap candidates who confuse management levels.

How to eliminate wrong answers

Option A is wrong because Managing Product Delivery is the process used by the team manager to manage the work of creating project products and does not involve the Project Board giving direction. Option B is wrong because Controlling a Stage is the process used by the project manager to monitor and control the day-to-day work within a stage, not for the Board to give ad-hoc direction. Option C is wrong because Managing a Stage Boundary is the process used by the project manager to prepare a stage plan and provide information to the Board for end-stage assessment, not for ad-hoc direction.

498
MCQeasy

What is the purpose of the Starting Up a Project process?

A.To check if the project is worthwhile and can be delivered
B.To manage the day-to-day activities of the project
C.To close the project in a controlled manner
D.To produce the Project Initiation Documentation
AnswerA

Correct. SU ensures basic conditions exist before initiating.

Why this answer

Starting Up a Project is a pre-project process to ensure that the project has a viable business justification and that the necessary people and resources are available before committing to the full initiation stage.

499
Multi-Selectmedium

Which TWO of the following are activities performed in the Managing a Stage Boundary process?

Select 2 answers
A.Authorise a Work Package
B.Produce the Project Brief
C.Update the Business Case
D.Plan the next stage
E.Deliver a product
AnswersC, D

Business Case is reviewed and updated in SB.

Why this answer

SB includes updating the Business Case and planning the next stage. Authorising Work Packages is done in CS, and delivering products is done in MP.

500
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Continue and report in the next Highlight Report
B.Close the project
C.Raise an Exception Report to the Project Board
D.Increase the project budget and continue
AnswerC

PM escalates via Exception Report for decision.

Why this answer

PRINCE2's management by exception requires escalation via an Exception Report when tolerances are forecast to be breached.

501
Multi-Selecteasy

Which TWO of the following are purposes of the Managing Product Delivery process?

Select 2 answers
A.To plan the next stage
B.To accept and execute Work Packages
C.To manage stage boundaries
D.To close the project
E.To deliver completed products to the Project Manager
AnswersB, E

Core purpose of MP.

Why this answer

MP aims to accept and execute Work Packages and deliver completed products. Planning the next stage is done in SB. Managing stage boundaries is SB.

Closing the project is CP.

502
MCQeasy

Who is responsible for ensuring that the Business Case remains viable throughout the project?

A.Project Manager
B.Senior Supplier
C.Senior User
D.Executive
AnswerD

The Executive owns the Business Case and is responsible for its viability.

Why this answer

The Executive (Senior Responsible Owner) is accountable for the Business Case and ensuring its ongoing viability.

← PreviousPage 7 of 7 · 502 questions total

Ready to test yourself?

Try a timed practice session using only PRINCE2 Processes questions.