During the Closing a Project process, what is the purpose of the End Project Report?

⚠ Common exam trap

PRINCE2F often tests the confusion between the End Project Report and the End Stage Report, or between the report and the activities within Closing a Project, causing candidates to select an answer that describes a different management product or process activity.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

To summarise project performance and lessons learned

The End Project Report is a PRINCE2 management product created during the Closing a Project process. Its core purpose is to provide the Project Board with a summary of the project's overall performance against its baseline (scope, time, cost, quality, benefits) and to capture lessons learned for future projects. It also confirms the project's final status and supports the Project Board's decision to authorize project closure. Option D accurately captures this dual role of performance summary and lessons documentation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    To obtain approval for the next stage

    Why it's wrong here

    Approval for the next stage belongs to the Managing a Stage Boundary process, where the next Stage Plan is authorised. The End Project Report instead reviews the project's overall performance. It is tempting because both are assurance documents, but the report is produced at closure, not at a stage boundary.

  • ✗

    To hand over products to the customer

    Why it's wrong here

    Handing over products is a distinct Closing a Project activity, performed via the Handover and Acceptance processes, not the End Project Report's purpose. It is tempting because both occur during closure, but the report evaluates the project's performance and lessons; it does not transfer deliverables to the customer.

  • ✗

    To update the Business Case

    Why it's wrong here

    The Business Case is updated during the Closing a Project process, but that is done by the project manager as a separate activity, not as the End Project Report's purpose. It is tempting because the report does feed lessons and performance data into the Business Case review, yet its own purpose is to report performance against the project's baseline.

  • ✓

    To summarise project performance and lessons learned

    Why this is correct

    The End Project Report summarises project performance against the baseline and records lessons learned, providing the Project Board with the information needed to confirm project closure. This satisfies the requirement to evaluate achievements and capture organisational learning during Closing a Project.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.