Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

During the Closing a Project process, what is the purpose of the End Project Report?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To summarise project performance and lessons learned

The End Project Report provides a final assessment of project performance against the PID, and is used to evaluate project success and inform future projects.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To obtain approval for the next stage

    Why it's wrong here

    End Stage Report is used for stage approval; End Project Report is for closure.

  • To hand over products to the customer

    Why it's wrong here

    Product handover is part of CP, but the End Project Report is separate.

  • To update the Business Case

    Why it's wrong here

    The Business Case is updated throughout; End Project Report is a summary.

  • To summarise project performance and lessons learned

    Why this is correct

    The End Project Report covers performance, benefits, and lessons.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.