PRINCE2F PRINCE2 Processes Practice Question
During the Closing a Project process, what is the purpose of the End Project Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To summarise project performance and lessons learned
The End Project Report provides a final assessment of project performance against the PID, and is used to evaluate project success and inform future projects.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To obtain approval for the next stage
Why it's wrong here
End Stage Report is used for stage approval; End Project Report is for closure.
- ✗
To hand over products to the customer
Why it's wrong here
Product handover is part of CP, but the End Project Report is separate.
- ✗
To update the Business Case
Why it's wrong here
The Business Case is updated throughout; End Project Report is a summary.
- ✓
To summarise project performance and lessons learned
Why this is correct
The End Project Report covers performance, benefits, and lessons.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.