During the Controlling a Stage process, the Project Manager receives a Checkpoint Report indicating that a product will be delivered late. What should the Project Manager do first?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Assess the impact on stage tolerances and take corrective action if within tolerance

If a Checkpoint Report indicates a deviation within stage tolerances, the PM can take corrective action themselves. If it threatens stage tolerance, they must escalate.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Assess the impact on stage tolerances and take corrective action if within tolerance

    Why this is correct

    Assessing impact on stage tolerances first satisfies the Controlling a Stage requirement to manage by exception. The Project Manager must determine whether the delay breaches delegated tolerance before acting; if within tolerance, corrective action stays at stage level, avoiding unnecessary escalation to the Project Board.

  • ✗

    Revise the Stage Plan and inform the Project Board

    Why it's wrong here

    Revising the Stage Plan and informing the Project Board pre-empts the exception assessment; the Project Manager must first evaluate the deviation against tolerances before deciding whether escalation is warranted. It tempts because Stage Plan updates and Board communication are legitimate Controlling a Stage actions, but only after the tolerance position is established.

  • ✗

    Request a new Work Package from the Team Manager

    Why it's wrong here

    Requesting a new Work Package misdirects the response: the Team Manager already holds the Work Package and reports progress against it, so issuing another does not address the late product. It tempts because Work Packages are the mechanism for authorising work, which would be right when allocating new work, not handling a checkpoint exception.

  • ✗

    Raise an Exception Report immediately

    Why it's wrong here

    A Checkpoint Report is an internal control point; the Project Manager first assesses the deviation against the Stage Plan tolerance before escalating. An Exception Report is only raised once a forecast breach of stage or project tolerances is confirmed, so raising one immediately pre-empts that assessment.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.