PRINCE2 Processes →easyMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

Who is responsible for ensuring that the Business Case remains viable throughout the project?

⚠ Common exam trap

PRINCE2F often tests the distinction between accountability and responsibility — candidates confuse the Project Manager's day-to-day responsibility for maintaining the Business Case with the Executive's ultimate accountability for its viability.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Executive

In PRINCE2, the Executive is the single individual ultimately accountable for the project's success and is specifically responsible for ensuring the Business Case remains viable throughout the project. The Executive owns the Business Case and must ensure that the project remains aligned with the organisation's strategic objectives and continues to deliver value for money.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager prepares and updates the Business Case on the Executive's behalf, but accountability for its viability remains with the Executive. The Project Manager role is tempting because day-to-day responsibility for maintaining the document is delegated to them, yet ownership of the justification itself is not.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents the supplier's interests and provides resources and delivery capability, not Business Case viability. Accountability sits with the Executive on the Project Board. The role is tempting because suppliers contribute cost and resource information that feeds the Business Case, but they do not own it.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests and specifies requirements, but does not own the Business Case. The Project Board holds that accountability, with the Executive responsible for the Business Case and its ongoing viability. The Senior User role is tempting because benefits realisation is often associated with users.

  • ✓

    Executive

    Why this is correct

    The Executive owns the Business Case, remaining accountable for its viability throughout the project. They judge whether the justification still holds at each stage boundary and can trigger premature closure if benefits no longer outweigh costs.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.