Question 228 of 892
Process — Managing Technical AspectsmediumMultiple SelectObjective-mapped

Quick Answer

The answer is work performance data and the project management plan. Work performance data is correct because the Control Schedule process relies on raw observations of actual start and finish dates and progress against the schedule baseline to calculate schedule variance and assess performance. The project management plan, specifically the schedule management plan, is also a key input as it defines the thresholds for variance and reporting formats used to control the schedule. On the PMP exam, this question tests your understanding of the distinction between inputs, tools, and outputs in the Monitoring and Controlling Process Group; a common trap is confusing work performance data with work performance information, which is an output, not an input. Remember the memory tip: “Data goes in, information comes out” — work performance data is the raw input you feed into the control process to produce meaningful reports.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO are inputs to the Control Schedule process? (Choose two.)

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project management plan

The Control Schedule process monitors the status of project activities and manages schedule changes. The project management plan (B) is a key input because it contains the schedule management plan, which defines how the schedule will be controlled, including thresholds for variance and reporting formats. Work performance data (C) provides the raw observations and measurements of actual start/finish dates and progress against the schedule baseline, which is essential for calculating schedule variance.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Schedule data

    Why it's wrong here

    Schedule data is an output of Control Schedule, not an input.

  • Project management plan

    Why this is correct

    The schedule management plan is a component of the project management plan and is an input to Control Schedule.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Work performance data

    Why this is correct

    Work performance data provides actual start/finish dates and is an input to Control Schedule.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Organizational process assets

    Why it's wrong here

    OPAs are inputs to Develop Schedule but not listed as inputs to Control Schedule.

  • Schedule forecasts

    Why it's wrong here

    Schedule forecasts are an output of Control Schedule.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is confusing inputs with outputs: candidates often select schedule forecasts or schedule data because they sound like 'data' needed for control, but PMBOK defines them as outputs generated during the process, not inputs.

Trap categories for this question

  • Command / output trap

    Schedule data is an output of Control Schedule, not an input.

Detailed technical explanation

How to think about this question

Under the hood, Control Schedule uses the schedule management plan from the project management plan to define acceptable variance thresholds (e.g., ±5% on critical path). Work performance data includes raw field data like actual start dates (AS) and percent complete, which is then analyzed using earned value management (EVM) metrics like schedule variance (SV = EV - PV) and schedule performance index (SPI = EV/PV). In a real-world scenario, if a construction task is 50% complete against a planned 70%, the work performance data triggers a variance analysis, and the schedule management plan dictates whether a change request is needed.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Project management plan — The Control Schedule process monitors the status of project activities and manages schedule changes. The project management plan (B) is a key input because it contains the schedule management plan, which defines how the schedule will be controlled, including thresholds for variance and reporting formats. Work performance data (C) provides the raw observations and measurements of actual start/finish dates and progress against the schedule baseline, which is essential for calculating schedule variance.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.