Courseiva
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

Your agile team has been experiencing conflicts between two senior developers over technical approaches during sprint planning. The conflicts are causing delays and affecting team morale. As the project manager, what is the BEST course of action?

⚠ Common exam trap

Many exam-takers confuse the project manager's authority with a directive role, leading them to choose option C (making the decision themselves) or option B (escalating), when the agile mindset requires servant leadership and team empowerment to resolve technical conflicts.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a meeting between the developers to discuss and resolve the technical disagreement

Facilitating a meeting between the developers is the best course of action because it directly addresses the root cause of the conflict—a technical disagreement—while empowering the team to self-organize and resolve the issue collaboratively. As an agile project manager, your role is to remove impediments and foster a safe environment for constructive debate, not to impose technical decisions or escalate unnecessarily. This approach aligns with the agile principle of building projects around motivated individuals and trusting them to solve technical problems, which preserves team morale and avoids delays caused by unresolved conflicts.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Facilitate a meeting between the developers to discuss and resolve the technical disagreement

    Why this is correct

    Constructive conflict resolution through facilitated discussion promotes team cohesion and decision-making.

  • Escalate the issue to the functional managers of the developers

    Why it's wrong here

    Escalation should be a last resort; the PM should first attempt to resolve the conflict within the team.

  • Make the technical decision yourself to end the debate

    Why it's wrong here

    The PM should empower the team to make technical decisions; imposing a solution can undermine team ownership.

  • Assign the developers to different teams to avoid future conflicts

    Why it's wrong here

    Removing a senior developer from the team avoids the immediate conflict but fails to address the root cause of technical disagreement, which an agile coach or facilitated negotiation would resolve through shared decision-making. It is tempting because reassignment is a quick structural fix for interpersonal friction, and it would be correct if the conflict stemmed from incompatible skill gaps rather than differing technical opinions on the same sprint backlog.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.